m = 'most likely' time
o = 'optimistic' time
p = 'pessimistic' time
You can then estimate the expected time 'e' by modelling a triangular distribution based on these and sum the estimates on the critical path. e = ∑(oi + 4mi + pi)/6
This is actually a very useful technique but sadly is done very infrequently (probably because it usually comes up with an number that people don't want to hear - but is usually much more realistic).[1] https://en.wikipedia.org/wiki/Program_evaluation_and_review_...
The program (or project) evaluation and review technique, commonly abbreviated PERT, is a statistical tool, used in project management, which was designed to analyze and represent the tasks involved in completing a given project. First developed by the United States Navy in the 1950s, it is commonly used in conjunction with the critical path method (CPM).