>Presuming that you're delivering more responsively and quickly to the customer than you were before, which you didn't mention
In the interest of full disclosure, I think we had a project time over-run of 2x (estimated 4 months to 8 months) mainly due to "feature creep" (is that a feature or a bug in Agile iterative cycles?); the project is a high-throughput data pipeline for genome sequencing and annotation. We overran time as a case of our customers/users wanted to add more bells and whistles to the tail end of the pipeline as they saw the end product more and more and proposed more added steps.