Source?
> Most European transformers are three-phase and on the order of 300 to 1000 kVA, much larger than typical North American 25- or 50-kVA single-phase units.
Systems which run a higher consumer voltage (e.g. 230V) will tend to use higher kVA transformers compared to the American system (~110V).
I believe this is because it is feasible to run longer cables when using higher voltage (higher voltage -> lower current -> lower thermal losses per metre of cable), hence it is economical to use fewer, larger transformers in a higher voltage system vs. a lower voltage system.
However, even here the network transformers do get three-phase.