Ask HN: Is there academic research on the effectiveness of estimation in scrum?
It would be especially interesting to see results about improvement of accuracy over time.
"The most surprising part of the 1985 Jeffery-Lawrence study appeared at the very end, when they investigated the productivity of 24 projects for which no estimates were prepared at all. These projects far outperformed all the others (see Table 5-3)."
Table 5-3 Productivity by Estimation Approach (Full Result)
-----------------------------------------------------------------------
Effort Estimate Prepared by Average Productivity Number of Projects
-----------------------------------------------------------------------
Programmer alone 8.0 19
Supervisor alone 6.6 23
Promgrammer & supervisor 7.8 16
System analyst 9.5 21
(no estimate) 12.0 24
Source: https://www.amazon.com/Peopleware-Productive-Projects-Teams-...https://www.iancarroll.com/2016/04/18/no-correlation-between...
This person has done some stuff on some aspects: https://collaboration.csc.ncsu.edu/laurie/publicationsAll.ht...
Since you need multiple teams, building similar software in order to compare.