when you estimate the tasks independently you sometimes over-estimate sometimes under-estimate and the errors compensate each other.
Not in my experience. Under-estimate errors are basically always much smaller than over-estimate errors. Unknown factors that can dramatically speed up a projects are much fewer than unknown factors that can dramatically slow down a project.
I mean if nothing else a 4 week task can, at best, be delivered 4 weeks early, but there is no upper limit to how late it can be.