The article reads as though the $60 million is fully installed and commissioned.
Sounds like your $1/watt is for the panels only?
You'll probably want to get them freighted to the installation site, screwed down to a support frame, wired up to an inverted, connected to a load and / or the grid.
This may drive the price up somewhat.
What I might be more concerned about is that their agreement to sell power is only for two years. Without storage, they may have a hard time getting good prices for mid-day power in the near future.
Edit: Probably $1.50/watt for utility scale: https://pv-magazine-usa.com/2016/09/29/nrel-u-s-utility-scal...