For everyone (n00b to senior) I would always recommend designing & breaking things down into no smaller 1/2 day blocks, where nothing went longer than 3 days (for inexperienced), but longer for more experienced. Senior devs should be able to be able to be trusted (to be accurate) for week-long blocks.
Use a Gannt chart (ms project or similar) and monitor the inexperienced, gauging their real-life times with their estimates, adjusting accordingly. Give semi regular feedback at the accuracy so that they (& you, the manager) are working with.
In one of my companies, the most inaccurate we were for any project was that we were late 2 days over 2 years. Build on trust, build on meetings and other time sinks. Include testing, sign offs, etc.
So, absolute n00bs need close mentoring so that the (senior) mentor can begin to gauge the growth rate... Which will be steep... But different for everyone.