It sounds to me like you guys are estimating in hours, thus you give an 8 hour estimate, they expect something to be done 8 work hours after you started work. Everyone knows you have 80 hours in a two week period so they expect you do finish 10 of these 8 hour tickets.
Compare that to Story Points. Your velocity over a two week sprint is auto adjusting for the typical/average meeting load and other interruptions. If you estimate a ticket at 8 story points and your velocity is 24 story points then everyone should expect you to finish 3 of these tasks per sprint.
This is obviously all 'on average' and there might be a production incident that means this time you didn't get it all done or maybe the other way around, someone got sick and 3 large meetings didn't happen and you got a 4th ticket through.
Also note that I chose 8 story points at random. 8 story points is specifically NOT to be equated with 8 hours. Story points are just uses as a relative complexity measure, meaning something with 3 story points is roughly a third as complex as that 8 pointer.
Many managers and even people that claim to be Scrum Product Owner or even Scrum Masters don't really understand that.