How the Fehmarnbelt Tunnel is being built [video]
youtube.com
youtube.com
I would also be interested to know what the tunnels effective weight will be once it’s submersed. Given the sections are hollow, the road and train sections will create a buoyancy effect. Possibly enough to offset the total weight of the concrete, given they need to fill ballast tanks in-order to sink the sections. If that’s the case, they can probably adjust the ballast tanks to keep the sections near to neutrally buoyant, and thus apply little pressure to the sediment below.
For the record, I don't think I'm "gotcha-ing" the engineers by thinking of these questions. I'm sure there have been answer to these questions since before the project began, it's just that I would like to know the answers.
They also must have a way to seal off segments in case of a water breach? Although, that seems awful given there will be human traffic in the tunnel
After putting in a segment, the trench is backfilled with rocky material (over the segment), so that any buoyancy is negated by the fact that it's held down by a large layer of rocks. This layer presumably also prevents most, if not all, leaks from generating instant floods in the tunnel.
Lastly, once completed the project will result in 5 parallel, but mostly independent tunnels (two train tunnels, two highway tunnels, and a service tunnel between the highway tunnels). I presume that the tunnels can be isolated and waterproofed seperately.
> The precast concrete tunnel sections will have a rectangular cross-section that is about 40 metres (130 ft) wide and 10 metres (33 ft) high
and (also mentioned in the video):
> The tunnel will consist of 79 standard elements with a length of 217 metres
If it's a perfect cuboid, this should result in a buoyancy corresponding to ~87,000 tonnes. According to the video, each segment weighs (over) 73,000 tonnes, though this presumably doesn't include other stuff that will be added into the tunnel like road surface material, rail tracks etc.
[0] https://en.wikipedia.org/wiki/Fehmarn_Belt_Fixed_Link#Tunnel...
So it appears they will not be buoyant.
Trelleborg’s Gina gaskets and Omega seals fit between the sectional elements of immersed tunnels to prevent water ingress due to external water pressure.
Designed to handle intense transfer of hydrostatic loads and movements between tunnel ends caused by environmental pressures such as seismic activity, soil settlement and temperature effects, Trelleborg’s sealing systems promise a product life expectancy of up to 120 years with little-to-no maintenance.The other things you might worry about is expansion and contraction due to temperature changes, and even just minor size differences in manufacturing (for instance when using moulds to manufacture concrete, those moulds themselves might not all be perfectly the same size or they might change over time). So often in concrete bridges (or even concrete/steel pipes) there will be "joints" designed to absorb changes within some tolerance (eg with pipes, there's typically a rubber gasket that keeps things air/water tight while also allowing some compression/expansion).
Point is, I don't think one could model the Fehmarnbelt tunnel as open air or assume that the surrounding material is an infinite heat sink.
https://citymonitor.ai/transport/londons-tube-has-been-runni...
The tunnel segments have ballast tanks which are empty during towing, then are filled with water to increase the density of the segment and sink it to the ocean floor.
And regarding air management, in Japan and HK at least, driving through lengthy tunnels can already be a stinky affair, especially in summer, so ensure your vehicle's air conditioning system is set to cycle the air inside the car. The Tokyo Bay Aqua Line tunnel that connects Yokohama to Chiba is quite long and it uses large fans that vent at mid-way points, one doubling as a tourist stop. The Fehmarnbelt tunnel being the longest in the world is therefore longer, and I didn't see such venting points. Yes I noted the air movers in the video. But hey, I'm hopeful that such problems will attenuate with electrification.
Oil rigs definitely follow the prefabrication and then float-into-position approach, and have been doing that for a long time.
I'm sure there's a good reason why it's more cost effective or feasible to do this instead of drilling a tunnel under the seabed.
If you're ever in or around Normandy I highly recommend a visit to the beaches. They're much bigger than I had imagined, and it really hit home then what a massive operation it was.
Anyway – no, the technique is not new.
The first tunnel constructed with this method was the Shirley Gut Siphon, a six-foot sewer main laid in Boston, Massachusetts in 1893. The first example built to carry traffic was the Michigan Central Railway Tunnel constructed in 1910 under the Detroit River, and the first to carry road traffic is the Posey Tube, linking the cities of Alameda and Oakland, California in 1928. The oldest immersed tube in Europe is the Maastunnel in Rotterdam, which opened in 1942.
[1] https://www.betoningenieure.de/dateien/FT2018/Seiten/fehmarn...
A Caisson is like an upside down boat turned into a diving bell that is used to get access to the seafloor.
https://en.wikipedia.org/wiki/Caisson_(engineering)
Famously used in the construction of the Brooklyn Bridge
https://fromthepublicdomain.com/2020/08/26/the-brooklyn-brid...
10 minute documentary on Brooklyn Bride https://www.youtube.com/watch?v=Ct_-0GC_QfM
The Ken Burns' documentary is really worth a watch, https://en.wikipedia.org/wiki/Brooklyn_Bridge_(film)
The Mose in Venice (though it is a sort of foldable dam) has inside a tunnel for maintenance and it was built in a similar way:
https://en.wikipedia.org/wiki/Caisson_(engineering) disagrees. It distinguishes between box caissons and open caissons.
When dry, inside can detach a bulkhead, remove surplus grout from new unit, and remove it's bulkhead in turn. It's shallow water so doesn't need high pressure resisting caulk seals to be mostly watertight.
They say 15mm tolerance. You could butt fit rubber or polystyrene foam to keep things mostly OK and.. grout.
It's between Denmark and Germany. You can look it up. No, it isn't in an earthquake zone.
https://www.penta-ocean.co.jp/english/business/civil/crawnci...
Hope it's worth it.
[0]: [pdf] https://vvmdokumentation.femern.dk/39.%20E6TR02217843.pdf?fi...
If we want people to start taking CO2 into consideration when designing projects, it needs to have a cost associated with it. Ideally that cost should be used to offset the CO2 emitted. It wouldn't solve any issue but it will incentivize solutions that use less CO2.
The real positive impact it would have though is incentivizing lower carbon development: if traditional concrete has unpriced carbon emissions, there's no incentive for a design to specify using a low carbon alternative that might cost slightly more.
Yes. Since the issue is we've emitted too much CO2, the solutions are either to not emit it, or to remove it after emission. You set the price to whatever the actual cost is to remove it, and that lets the person do the emitting decide if it is worth it to emit, or if it would be cheaper to use an alternative. I view that as the reasonable minimum price.
If we were looking to go carbon-negative to start to undo decades of harm, you would want the carbon price to be higher than the removal cost.
> Average estimate is closer to $50/tonne.
Where did this number come from? I've never heard it. It doesn't line up with the goals of Canada ($50 this year, targeting $170/t in 2030), and the spot price in the EU was 85 euro in December.
There are more than just these two options. For example, you can capture CO2 at the emission site, which is much cheaper than doing the same after it dissipates to low concentration in the atmosphere.
> If we were looking to go carbon-negative to start to undo decades of harm, you would want the carbon price to be higher than the removal cost.
While preventing future bigger changes to climate might be worthwhile, I for one believe that imposing enormous burden on entire world just so that we revert to CO2 levels from, say, 1950, is simply not worth it. Say what you want about future climate “catastrophe”, but as of today, we are just fine.
> Where did this number come from? I've never heard it. It doesn't line up with the goals of Canada ($50 this year, targeting $170/t in 2030)
See eg.
https://www.edf.org/true-cost-carbon-pollution
https://www.irena.org/-/media/Files/IRENA/REmap/Methodology/...
Etc. The figures you are quoting are just politicians trying to get more tax money through climatewashing, these have nothing to do with actual externalities of GHG emissions or with mitigations.
If this project captured the emissions at the site, then they wouldn't have to pay the hypothetical carbon fee. That would be a reasonable option for the designer to consider (along with low carbon concrete or just building it and paying whatever fee it would entail)
> While preventing future bigger changes to climate might be worthwhile, I for one believe that imposing enormous burden on entire world just so that we revert to CO2 levels from, say, 1950, is simply not worth it. Say what you want about future climate “catastrophe”, but as of today, we are just fine.
The climate is an inherently unstable system - we're still dealing with the effects of carbon emissions from decades ago. If we stopped all carbon emissions now, the climate wouldn't stabilize for centuries or millennia.
> https://www.edf.org/true-cost-carbon-pollution
From your source, "The current central estimate of the social cost of carbon is over $50 per ton in today's dollars. While this is the most robust and credible figure available, it does not yet include all of the widely recognized and accepted scientific and economic impacts of climate change. For that reason, many experts agree [PDF] this is far lower than the true costs of carbon pollution."
> https://www.irena.org/-/media/Files/IRENA/REmap/Methodology/...
Dated literature review, relying largely on a US government document from 2013, which was itself updated in 2016 for being inaccurate
The IPCC was estimating 135-5500/t in 2018, though criticism was fairly levelled that current economic models can only estimate impact of implementing moderate carbon costs. https://www.resources.org/archives/latest-ipcc-report-sounds...
> The figures you are quoting are just politicians trying to get more tax money through climatewashing, these have nothing to do with actual externalities of GHG emissions or with mitigations.
Disagree strongly. Also, the carbon market in the EU and the climate costing in Canada - neither of them goes into general tax coffers.
Which is a bit weird: Why have those pontoons on the surface in the first place? They could provide just as much buoyancy if they were tethered just above the tunnel itself, at a depth of some tens of meters. Or below it, pushing upwards in stead of pulling. (This would also avoid any potential problems with ice dragging them sideways in the winter.)
ETA: If you're curious NYC has a dashboard of capital projects >$25 million here: https://www1.nyc.gov/site/capitalprojects/dashboard/dashboar.... I think the complaint that we don't build anything in this country anymore is sometimes overstated.
ESA was started in 2006 and planned to be finished in 2009 at the cost of $4.3B. It is now projected to be finished in 2023, at a cost of $12B.
Phase 2 of SAS costs $6B despite the fact that most of the tunnel actually already exists, and won't open until possibly 2029.
It's not even really about saving money to save money, but the high costs of these projects suck money away from other projects and needs. It's basically unfathomable at these prices for NYC to do something like Paris and build out 200 km (124 mi) of metro in the next decade.
Basically, instead of ESA and (ultimately cancelled) Gateway projects, calling for new tunnels connecting to giant carvern terminuses in the city, u connect these projects into one long tunnel without terminuses.
A terminus requires a lot of platforms and tracks because trains need to get completely emptied and turned around. If you stop at multiple stops and terminate at the other end of the city, you can do that a that a place where's plenty of space (or multiple different points). You also spread the passenger loads across multiple stations, meaning less passenger flow per station, less dwell time for trains (=higher frequency), and people will be closer to where they need to go (i.e. you can connect to all subway lines in Manhattan).
Not only is that far more recent than 50 years ago, it's also in the Bay Area.
"and the tunnel idea received support from a large majority of the Danish parliament in January 2011. By 2012, therefore, the completion date had been pushed back to 2021, and in 2014 was estimated to be 2024, and then in 2015 delayed further to 2028. In 2020 it was delayed to 2029."
Actual construction began in the 70s, and was subsequently suspended for another 20 years because of the city's poor finances. So that gets us closer to a merely ludicrous 30-50 year construction timescale instead of an egregious 100 year one.
[1]: https://en.wikipedia.org/wiki/New_York_City_Water_Tunnel_No....
https://en.wikipedia.org/wiki/Leonard_P._Zakim_Bunker_Hill_M...
VERY cool though
Jokes aside, there are sometimes rail projects where millions are spent to save 2 minutes. Or even just tens of seconds. Over the lifetime of the infrastructure it is still worth it, especially when combining multiple projects.
2 hours savings is huge. You won't find many infra projects with those kind of time savings.
Diagonal. The word you were looking for is diagonal. :-)
The ferry cost about three times as much as the fee for the Great Belt bridge to Fyn, so people use the ferry because they still save a couple of hours, depending on traffic.
So the bridge will make a huge difference.
Interestingly the ferry which is currently used to transport trucks is only at roughly half capacity.
It is a prestige project and I will have to move to some other place as I live next to the train tracks. These are used very sparingly today and are mostly not even electrified and one-tracked. Many wildlife refuges are on the way to move for the sake of the new tunnel.
By distance from Malmö to Hamburg is a bit farther than to Gothenburg and Berlin is a bit closer than Stockholm, with the forced dogleg of going through the Fehmarn Belt. By air it would be like Leipzig. That is how far into Germany you get.
It is simply ridiculous that the only way I could think of to get to the larger cities in northern Germany would be to fly. Take the train to Copenhagen airport and likely Ryanair or something similarly awful costing less than the ticket to the airport.
Sure I could look up some train travel with a multitude of changes through Denmark, likely taking the train on the ferry. Or an over night sleeper style, if they even run. I know there's been talk of them starting again.
It's 2022, there should be high speed links.
The new-ish night train runs direct from Malmö, but only in some months of the year. (A seats-only overnight train runs all year from Copenhagen. But that was not fun the one time I used it.)
Sometimes the existing solution doesn't need to be bursting at the seams to justify building something better. A better solution can induce its own demand.
There's a rail noise map for some lines in Denmark. Activate Temavælger - Jernbanerstøj - Større Jernbaner 1,5m, and start at Copenhagen Airport, the Øresund line might be similar.
In Denmark this project would have been built in a year, in time and in budget. But unfortunately this involved Germany, so now they have another huge stinking overcost project. Denmark is angry
About construction delays and politicians getting in the way etc., I can only think of BER as a catastrophic project. Do you have more in mind?
In Cologne a tunnel collapsed during construction, killing two people: https://en.wikipedia.org/wiki/Cologne_Stadtbahn#Tunnel_colla...
https://www.tunnel-online.info/en/artikel/tunnel__3596417.ht...
But apparently it's again stopped: https://www.dredgingtoday.com/2022/01/19/leipzig-court-tempo...
Overview: https://en.wikipedia.org/wiki/Fehmarn_Belt_Fixed_Link
There should be better articles about the cost overruns.