Finland starts much-delayed nuclear plant, brings respite to power market
reuters.com
reuters.com
They'll probably shut the plant down, and have 500 workers come in to replace everything that needs to be replaced, and then power it up again within a few days, and let it run for another 6 months or so.
Everything will be planned on workplans, and most won't require specialist knowledge... Eg. "Replace pump 205 in building C with this pump. Required skills people: 2x plumber, 2x electrician".
Most reactor maintenance is already done during refueling so there isn't much more room to optimize that downtime. (though that may change the older a reactor gets)
Finland is actually somewhat known for running short (1 year) cycles with very very short (<10 days for refuelling is not unheard of) refuelling outages every other cycle alternating with slightly longer maintenance outages. A more typical scenario in the US would be 18 month cycles with a 30ish day outage. Some plants are moving to 24 month cycles with slightly longer outages.
Capacity factor for nuclear plants in the US is consistently around 93% (similar figures in many other countries as well), which is significantly higher than other generation sources.
This is called demand response, https://www.energy.gov/oe/activities/technology-development/..., and it's probably as important of a component to future grid management as energy storage.
Bitcoin mining is commonly promoted as this kind of ideal electricity consumer. Hydrogen production could be another.
However, I think more interesting for this community would be to build some kind of demand response general computing datacenter. Basically, sell computing resources with poor availability guarantees, but at a cheaper rate than standard datacenters.
i.e. we'll run your batch jobs very cheaply, but we can't give you strong guarantees about how long it will take because we have to wait for excess grid electricity to have the energy to run them. Best case that's every night. Worst case we won't be able to run anything for weeks because Texas is going through another freak winter storm.
I think you misunderstood. The parent comment implied that excess electricity could be use to produce synthetic fuels (via carbon capture) to power conventional airplanes, ships or other machinery.
(edit - assuming everyone uses the same amount of power globally as the average person in Finland which - why shouldn't they be able to - and - obviously they don't)
Finland's climate is an outlier:
One-third of energy consumption in housing was electricity in 2018. [...] 47% of electricity was used to heat indoor areas and 36% to household appliances. The remainder of electricity was used to heat domestic water and saunas.
https://www.thenomadtoday.com/articulo/finland/energy-consum...
There's going to be an obvious error of margin either side of my napkin calculations but I think the order of magnitude is in the ballpark.
Whereas making something warmer can be done without a heat pump, by releasing stored chemical energy, at nearly no losses.
How many more meltdowns per decade?
The plants are also located away from cities, so utilizing the waste heat for district heating is uneconomical.
It’s like complaining that a wool blanket is itchy so it might be better to catch hypothermia and die.
That's hardly unique to nuclear plants; in particular, coal plants typically have lower thermal efficiency.
Energy generation is always a trade off. Right now the world is reacting to the fossil fuel funded wars created by one such trade off. We are also in the middle of causing irreversible climate change, which would cause more damage than any amount of meltdowns or nuclear waste could ever get near.
Naturally there are alternatives. If money were no objection then green hydrogen looks pretty nice, and one could always extract heat from the core of the earth as long the technology was safe enough to do so. As soon we have a technology that get proven to be cheaper, safer and more scalable than nuclear we should all switch to that. Buying natural gas from Russia is for multiple obvious reason not that.
Less radioactive EMISSION during NORMAL OPERATION than coal plants (and I think that ignores radioactivity released in uranium mining). The amount of radioactivity in the spent fuel rods of a nuclear plant is vastly higher than that liberated by a coal plant.
BTW, your chance of dying from cancer in your lifetime is about 20%, so I'm not sure that the 1/5 figure you gave there means anything.
There is a place in the US that has a rather peculiar name of Cancer Alley. It is not a nuclear testing area, nuclear waste deposit area or area for nuclear plants. It is an area know for its petrochemical plants. It illustrate quite well the difference of nuclear waste that people are scared of, and fossil fuel waste that people accept as just normal part of life.
In Finland's case, the realistic alternatives are burning coal or burning Russian gas. (If the Finns dedicated a substantial chunk of their forests to this one generator, they could maybe use biomass.)
Coal kills two orders of magnitude more people per GWh than nuclear--and it does that when operating nominally, not when malfunctioning--and it produces three or four orders of magnitude more waste and more environmental harm from mining.
Russian gas has geopolitical/national security problems.
Biomass is a roundabout way of burning diesel fuel and gas, while degrading and eroding forest soils and polluting watersheds.
The number of new meltdowns per decade rounds to zero, to five significant figures.
That's a weird metric (one meltdown is quite a catastrophe) and the calculation seems suspicious too. Between Chernobile and Fukushima I don't see how this could be correct.
I do find your other points more convincing, though with some "citation needed" wrt. coal.
And that's before we consider the environmental and health risks of ash ponds[2], which can (and have caused) heavy metal pollution in nearby groundwater supply. The largest industrial spill in US history happened barely a decade ago, and was an ash pond[3].
Edit: I can personally recommend "The Buffalo Creek Disaster" (ISBN 9780394723433) as a writeup by a lawyer involved in a similar coal ash accident (one that directly killed over 100 people).
[1]: https://www.pnas.org/doi/10.1073/pnas.2017936118
[2]: https://en.wikipedia.org/wiki/Ash_pond
[3]: https://en.wikipedia.org/wiki/Kingston_Fossil_Plant_coal_fly...
Maybe the problem is the uranium mine tailings are safely off in some poor country, not in the US where the coal ash would be?
https://en.wikipedia.org/wiki/List_of_countries_by_uranium_p...
Moreover the more we obtain uranium (prospecting, mining, milling...), the more we add to the associated carbon footprint. Therefore a sustained growth of installed nuclear capacity will lead us to exploit mines at always lowering ore grades => more emissions.
Scientific studies are clear: M. Lenzen ("between 10 and 130 g CO2-e/kWhel, with an average of 65 g") and E. Warner et G. Heath ("9 to 110 g CO‐eq/kWh by 2050")...
https://www.researchgate.net/publication/222817608_Life_cycl...
The popular YouTube channel The B1M has an interesting video on how Finland is tackling nuclear waste:
Finland might have solved nuclear power's biggest problem (2021): https://www.youtube.com/watch?v=kYpiK3W-g_0
And even after all that it's still far less expensive than remediating coal output.
Hoping to know enough and for sure about all this is... a hope.
Stating that we know what our descendants will need/do in a so distant future is even more funny.
They "considered" such facts using a somewhat light approach: 'Bob Loux, the executive director of the Nevada Agency for Nuclear Projects, expressed amazement that the US Department of Energy had only just carried out the "11th hour" drilling tests.
"It certainly looks like DoE has encountered a surprise out there, and it certainly speaks to the fact they haven't done the technical work they should have done years ago," he told the paper.
"It's going to have to cause some change of the design in the final analysis. It's going to impact the safety case."'
Source: https://www.theguardian.com/world/2007/sep/25/usaOops...
They also "considered" those metal containers as adequate during the 1990's, then... (what, you think "they" are omniscient?)... problems related to brines and high temperature arose...
https://www.nwtrb.gov/docs/default-source/board/mrs_duquette...
https://www.nrc.gov/docs/ML0335/ML033500420.pdf
Oops...
Just as you wouldn't factor Amelia Earhart's plane into 2022 air safety prognoses, you shouldn't use Chernobyl reactors for nuclear safety.
Nuclear fision reactors safety technology have moved further. There are challenges, but we havent even tried to solve them fully (as we were busy improving gas burning efficiency)
The RBMK reactor is quite an elegant design. Simple plug-and-play architecture for adding and removing fuel and other assemblies while the reactor was running, perfect for things like doping silicon for semiconductors and producing plutonium for weapons. But to get this capability you have to either give up affordability or safety, and they chose to give up safety.
TMI and Fukushima were both "modern" when built. All reactors that melted down did because operators ignored construction, maintenance, or operating safety standards. Other plants not yet melted down show evidence of more construction standard failings: pumps installed despite failing to meet specifications, bolts of substituted, inadequate steel. Diablo Canyon is built directly on a fault line. Now we learn that new EPR plants are inherently flawed, by design.
Ignoring standards is, by the evidence, itself standard procedure for building and operating civil nuke plants. Our global society, as it is conducted, is by the evidence unable to produce and operate a safe civil nuke.
[1]https://en.wikipedia.org/wiki/Diablo_Canyon_Power_Plant [2]https://en.wikipedia.org/wiki/Kori_Nuclear_Power_Plant
This is an understatement. The three largest nuclear power reactors in the world (Taishan 1, Taishan 2 and Olkiluoto 3) are all EPRs.
It is feared that all other current EPR suffer the same design mistake, but there are currently no plan to stop them.
A few people were vocal about this before it happened, and things did not go well for them. The Maureen Kearney case is simply unbelievable, this woman was working for Areva and blowing the whistle hard on this transfer of technology, after receiving threat she was found tied up in her bedroom, a letter A engraved in her abdomen, with a kitchen knife handle inserted in her genitals.
The police decided she probably did that to herself and jailed her, while the state attorney prosecuted her. And she was sentenced to prison time and a hefty fine. it took a while before the sentence was overturned and for the truth to come out that she had not faked anything.
In the end, what she was warning actually happened, France is no better and even worse in its ability to build nuclear plants with no actual plant put in service (ITER is a mess, Flamanville EPR is plagued), while China started both Taishan EPR reactors and is now able to sell its ability to build plants to other countries.
Nuclear, as it stands, is the only solution to decarbonizing the energy grid for much of the world. Until some breakthrough in energy storage transpires, or fusion becomes feasible, fission plants remain necessary for decarbonization.
Storage cost is falling much faster, even, than solar and wind generation. The only question today is whether to put a euro into solar or wind now, or into storage that will be much cheaper next year. Thus far, in most places, the former is still favored. More carbon tax can help move the choice the other way.
As solar and wind costs continue down, synthesizing methane and kerosene from captured CO2 and synthetic hydrogen will shortly be cheaper than mining, refining, and transporting them, even without the carbon taxes. Synthesis of those, and of ammonia and hydrogen itself will absorb unlimited "overbuilt" peak generating capacity, and stocks of all of those serve also as storage. That their round-trip efficiency is less than, say, hydro or batteries matters little where they rarely need to be used for that.
In response to your edit:
> As solar and wind costs continue down, synthesizing methane and kerosene from captured CO2 and synthetic hydrogen will shortly be cheaper than mining, refining, and transporting them, even without the carbon taxes. Synthesis of those, and of ammonia and hydrogen itself will absorb unlimited "overbuilt" peak generating capacity, and stocks of all of those serve as storage.
Nobody has successfully built a grid-scale energy-to-gas plant, ever. It remains the stuff of prototypes. This approach is very much in the "hypothetical" phase. There are serious unsolved problems in energy-to-gas:
* It needs a source of carbon to convert H2 to methane. This could come from biofuels, but those aren't available in sufficient supply.
* Producing large quantities of hydrogen without CO2 emissions remains difficult. Almost all methane comes from steam reformation (CH4 + 2O2 -> CO2 + 2H2), which emits carbon dioxide. Electrolysis can't be done effectively.
Currently, power to gas storage is way more expensive than either lithium ion or hydroelectric storage and it's unclear whether it'll ever be cheaper than existing options.
1. https://www.spglobal.com/marketintelligence/en/news-insights...
And, obviously hydrogen will not continue to be made from hydrocarbons. It will instead be feedstock for synthesizing hydrocarbons. Carbon would need to be extracted from air, or at least from exhaust, to get carbon credits.
In short, converting electricity to methane and then back to electricity again is not a presently available option and it's unclear whether it'll ever be viable at stale. Grid-scale energy storage remains an unsolved problem
Other storage media being built out for full-scale production use include iron-air batteries, where (IIRC) $1.5B is going into factories, a liquified-air storage system in Chile ($0.5B), and synthetic ammonia in Norway. Nobody can track even a fraction of the utility-scale pumped-hydro projects under construction world-wide.
We will need hundreds times as much of these, and of others, in the end, which will all take decades to build out.
You said it'd be stored in caves, so perhaps it's a different project. It'd be good to link to this project.
The Utah project looks like it's still trying to secure funding, and hasn't broken ground. https://power.mhi.com/regions/amer/news/20210511.html#:~:tex....
Similarly in Texas. The plans for this project were unveiled only a couple weeks ago: https://www.prnewswire.com/news-releases/green-hydrogen-inte...
Nobody announces billion-dollar physical construction projects for untested tech.
Things still being built need to finish being built before they go into service.
Just yesterday, you said some unspecified "breakthroughs" would be needed. Now you point to construction not finished. You are clutching at straws. The more honest course would be to admit you were just wrong.
Energy storage is far from a solved problem. You insist that it's been solved, but none of your proposed solutions have actually been implemented.
That is not to say there won't be breakthroughs, too, that make storage even cheaper to build out. But any storage already built will continue working as well as ever. Any hoped-for breakthroughs that don't pan out will not stall build-out. The worst that can happen is costs plummeting not quite as precipitously as had been expected.
We already see utility-scale hydro storage in use, and utility-scale iron-air battery factories under construction, and utility-scale liquified-air and ammonia-synthesis plants under construction, and utility-scale investment in hydrogen synthesis and storage. Each additional storage technology that begins to come online only improves the picture.
Repeating, again and again, that things that still need to be built out have not been built out yet sheds no light.
It is so economical nonviable that there isn't even small scale experiments to get the ball running as a storage medium. There is however some bright spots for green hydrogen when hydrogen itself can be used. Green hydrogen is only a few times more expensive than using fossil fuel in order to create hydrogen, and in that situation green hydrogen has found a place. It also reduces those industries CO2 emissions which can then be turned into profits in terms of trading existing emissions rights. As fossil fuels prices goes up, the economical viability of green hydrogen in hydrogen using industries goes up, but the price compared to nuclear remain the same.
In the mean time, nuclear is a nice thing to invest in.
Even a massively-nuclearized France produces 7% to 12% of its gridpower thanks to fossil-fuel plants.
French official historical data: https://www.statistiques.developpement-durable.gouv.fr/editi...
Pertinent document (French ahead!): https://new.sfen.org/rgn/expertise-nucleaire-francaise-suivi...
« un réacteur peut varier de 100 % à 20 % de puissance en une demi-heure, et remonter aussi vite après un palier d’au moins deux heures, et ce deux fois par jour »
Proposed translation: "a reactor power output can vary from 100% to 20% in 30 minutes, then after 2 hours can go back to 100% at the same speed, and can cycle this way 2 times per day".
This is quite a good performance when it comes to load-following (French engineers are very good at this), however it is insufficient in the real world (save any ridiculously expensive over-provision of nuclear reactor, most idling) and very weak compared to gas turbines performances.
"The Olkiluoto plant consists of two boiling water reactors (BWRs), each producing 890 MW of electricity, together comprising 22% of the country's electricity generation for 2020.[1] A third reactor, Unit 3, is expected to be online in January 2022, and at 1,600 MW, will by itself satisfy 14% of the country's electricity demand."
And many reactors are able to modulate their output, either by absorbing neutrons to slow the chain reaction, or by letting steam bypass the turbines.
https://www.energy.gov/ne/articles/3-ways-nuclear-more-flexi...
In any case, the cost/kWh from nuclear is computed assuming it's running flat out (except for refueling outages). Reduce that generation and the levelized cost increases. It's already very much higher than renewables; curtailing nuclear output would make that discrepancy worse.
Note that even some of the OPERATING costs of a nuclear plant are fixed. You still need about as many staff to run the plant even if you cycle it up and down.
The renewables will be wind and PV. Biomass uses too much land area, and would likely be reserved for specialty markets like chemical feedstocks and perhaps aviation fuel.
?? What renewable isnt given that?
Nuclear works when you want it to. Solar and wind work when they want to. That's a very big difference when you're producing the electricity people rely on to live their daily lives.
Hydrogen can be much cheaper for (say) the last 10%, because (1) hydrogen has very low capital cost per unit of storage capacity, and (2) the efficiency hit of going through hydrogen vs. batteries is less important when it's just 10% of the total.
Think of batteries and hydrogen as analogous to cache memory and main memory in a computer. They have different performance and economic characteristics and compensate for each others weak points.
To see this in operation, go to https://model.energy/ and try turning hydrogen off and on in the settings. If you simulate for Germany, for example, turning off hydrogen can double the cost of achieving a certain level of constant grid power. Hydrogen can be particularly valuable for places with large seasonal variation or lots of wind (which has a long timescale component in how it varies.)
I will add that China is already selling electrolysers for < $300/kW, less than half that simulation's 2030 cost assumption.
Basically all hydrogen comes from fossil fuels. It's just natural gas with extra steps.
When describing hydrogen for energy storage in a 100% renewable grid, the hydrogen would be produced by electrolysis using renewable energy.
I once compared a proposed pumped hydro system in Arizona near Phoenix vs. the water evaporated by the Palos Verde nuclear generating station. Per unit of levelized power output, the pumped hydro system used at least an order of magnitude less water than the nuclear plant.
If the panels don't mind settling on the banks, or if they are far enough offshore not to, that will not be a problem. It is already common to float panels on regular hydroelectric generation reservoirs, so the event is anyway familiar to operators.
If the floats are bottom-heavy and attached to cables spanning the reservoir, the water dropping out from under just leaves them suspended. You need cable attachments, anyway, to extract power and maintain spacing.
Nuclear provides a path for decarbonization. Solar and wind do not, until a massive breakthrough in energy storage is invented. And nobody knows when that will happen, or if it will happen.
As for storage, one way to "store" energy is hydrogen, which we can then burn as needed. We can probably get the efficiency of that to 70% (for hydrogen-burning larger-scale power plants).
Pumped-storage hydroelectricity is another existing option, with an efficiency of about 70-80%.
It's also OK to have some carbon emissions if you can manage to have other measures neutralizing that. We can e.g. use renewable biofuels (e.g. wood, biomass from algae or crops) which "use" a lot of carbon while growing to remove a lot of the emissions the power plants produce, and can with filter technology remove the rest to a degree where we'd still be neutral overall.
As I see it, we already got all the basic building blocks, and now it's a matter of optimizing them further and further, and more importantly figuring out the development and deployment (including financing, investment incentives, etc) and logistics (building the additional power lines required is a massive, politically-charged, often NIMBY-kind challenge here in Germany, and from what I hear in a lot of other places including the US too).
The deployment and logistics is a general problem of electrification, even with nuclear. People want to plug in their EVs near where they live, and want heat in their homes, so you either need additional power lines or (smaller scale) power plants close to people and industry, either way.
Decarbonization is maaaybe 1/4 of the way there, but folks seem to like to spin it as 90%.
You're absolutely right that we will need to spend a lot of money and time if you seriously want to achieve to become globally carbon-neutral. However, going nuclear wouldn't be necessarily cheaper or quicker, either.
Which makes a war of conquest or destruction by countries not doing so much easier to win.
Edit: Also, with interest rates likely to go up due to inflation/central bank action, that CapEx may soon be impossible to bear without some equivalent to a wartime economy anyway. A lot of the renewables have been helped by essentially free money.
You can see that in a lot of consumer products already, when the EU e.g. started to mandate to put energy consumption ratings on electric appliances, and the market then swiftly went to improve the power consumption in most cases. I grew up with regular light bulbs, but now I and everybody I know largely uses LED light bulbs, again driven by consumer demand and heavily nudged by political policy in the EU. And I either save money now or at least break even thanks to my electric bill being less, and LED lights usually lasting so long they are over time cheaper than the old regular bulbs.
I wouldn't dare try to predict how these things would actually shake out eventually.
Most of the easy improvements have already been done. with the possible exception of insulating more (far harder than changing out electric bulbs or when new appliances get bought or computers age out replacing them with higher efficiency versions). Normal ICE cars and trucks have also hit diminishing returns efficiency wise.
Usually not so easy though as it may seem, especially in concrete, stone, or other masonry buildings which are very common in Europe.
What I’m referring to is far coarser grained, and on the production side.
Fossil fuels are very, very energy dense, and that energy is released/used through completely different mechanisms than electrical energy. So for heat, even if switching to heat pumps which are over unity devices (1 Input unit of energy can move almost 3x units of heat), the amount of energy required to do so for countries which need a lot of heat is astronomical. I did some back of the envelope math for Germany in another thread, and even being very conservative we’re talking 7x the total energy requirements of their current entire grid to replace natural gas for them.
So it’s more than just buying a heat pump and installing it, it’s a massive undertaking involving the equivalent of $120-$600k+ of capex to accomplish. That is for every many woman and child when you add it all up. One would hope they could be more efficient, but those prices already involve a huge economy of scale.
If the EU forms an army and has mandated no fossil fuels, they would need to spend a massive amount more capex to build that army than if they did not right now, let alone keep it energized. That takes time, resources from other things, and exposes them to unique supply chain challenges too.
If they want to just switch their economy off fossil fuels, right now that will likely take a 5-10 years even on a wartime footing. It takes time to build factories, source materials, R&D complex things. Many of these will depend on countries they may not want to depend on (such as chips from China or raw materials currently sourced from Russia). And that is a massive amount of money, on top of likely weapons manufacturing, etc.
If they wanted to do it in 2 years, I’m not sure it’s possible right now.
These are geographically dependent. You can't build the where you need them.
> As for storage, one way to "store" energy is hydrogen, which we can then burn as needed. We can probably get the efficiency of that to 70% (for hydrogen-burning larger-scale power plants).
Large scale electrolysis remains unproven. This goes in the "scientific breakthrough required" bucket.
> Pumped-storage hydroelectricity is another existing option, with an efficiency of about 70-80%
Also geographically dependent. You basically need an alpine lake handy to build pumped storage.
Carbon sequestration at anything close to relevant scales also has never been done.
> The deployment and logistics is a general problem of electrification, even with nuclear. People want to plug in their EVs near where they live, and want heat in their homes, so you either need additional power lines or (smaller scale) power plants close to people and industry, either way.
No, this isn't a problem with nuclear. Most energy demand is in cities. And since nuclear plants are not geographically dependent, you can build them near places with lots of energy demand. As opposed to renewables which might need to be built very far away in places with large solar or wind potential.
Large-scale electrolysis is not unproven. E.g. Air Liquide operates a 20MW plant producing 3000t/annum near Quebec already[0]. Other projects in development aim for 200MW facilities. Granted, that isn't yet massive scale, just about 99,000 MWh/annum of usable energy (about 33kWh/kg for hydrogen), and the smallest US nuclear plant is theoretically capable of 5,098,320 Mwh/annum or around 50 times more. But large scale enough to act as a proof of concept in my opinion.
Pumped storage is a bit geo-dependent, but you do not need an alpine lake, you need an empty space somewhat higher up where you can pump some water, preferably without loosing too much water due to evaporation and other factors, and some water, preferably fresh water to avoid corrosion as much as possible, maybe desalinated. But if need be salt water and an artificial hill will do.
As for the deployment and logistics of nuclear, it is certainly a problem. Our current grids, independent from the form of electricity generation, are usually not designed to handle the growing demand that electrification probably will create. You can see what happens when the demand somewhat suddenly rises (and the EV introduction is still somewhat "sudden" in the time scales grid operators and infrastructure planners usually consider) e.g. in Kazakhstan when the Chinese bitcoin miners moved there[1]. Furthermore, planning, building and testing new nuclear plants is a massive capital expenditure even without technology research, as well as a political hot topic in a lot of places (and even in nuclear-friendly regions I'd bet that NIMBYs would form real quick once a location for a new plant gets discussed).
Last thing I read by the way is that the EU gets about 20% of the Uranium it uses to fuel existing nuclear plants from Russia (at least until now), with another ~20% coming from Kazakhstan[2], which is somewhat closely allied to (and for sure scared of) Russia. Another ~20% come from Niger, a country not exactly renowned for being a politically stable and human-rights respecting nation. Maybe the EU can source elsewhere, even if the demand increases as potentially more nuclear within the EU goes online, but it surely has a rather problematic political dimension attached aside from general nuclear politics such a nuclear proliferation. And it's not just the EU which needs to switch to electrification, either. Where will Africa or Latin America or Asia get their nuclear tech and nuclear fuel?
Nuclear, like oil, creates international political dependencies in a lot of places, while most renewables would not necessarily do the same.
[0] https://www.spglobal.com/commodity-insights/en/market-insigh...
[1] https://www.bloomberg.com/news/articles/2022-01-25/kazakhsta...
[2] https://ec.europa.eu/eurostat/statistics-explained/index.php...
The hydrolysis example you provided is tiny relative to the requirements of grid scale storage. To put this in perspective, the US alone uses 500 GWh of electricity every hour. And this will increase as electrification progresses, electricity only accounts for about a third of total energy production. Producing grid scale hydrolysis remains unproven.
The same reliance on a globalized economy still exist with intermittent sources. The copper used in wind turbine generators probably comes from Chile, for instance.
That will, of course, still need to be developed to production. But it is a (large) incremental process improvement, not a whole different technology.
First you said hydrolysis was not practical at all. Today you say 200 MW facilities are not big enough. What will you say tomorrow? Why not admit it now?
Throughout this whole thread you've been pointing to proposals and plans as though simply having plans is a demonstration of viability. Unless people are actively implementing the solutions you're proposing, then those solutions aren't proven to work. There's a massive difference between pointing to an entrepreneur that promises this special drill will be able to build geothermal plants anywhere, and actually building geothermal plants in the middle of Germany. There's a massive difference between plans that promise to store X amount of hydrogen, and actually building and running said storage plants. Electrolysis has been known for at
As far as I'm concerned, both hydrolysis and this geothermal-anywhere approach fall into the bucket of "scientific breakthroughs". Could they be viable if they pan out? Sure. But it's highly unwise to bet the future of civilization on something that might work out, as opposed to something that's been operating at scale for most of a century.
1. https://www.newscientist.com/article/mg21628955-900-laser-dr...
60 years, by the way, pushes the boundary of "most of a century".
Let's actually put this in perspective: Global electricity consumption is about 60 TWh daily, which works out to about 2.5 TWh per hour or 40 GWh per minute. Plans to run a wind and solar grid predict a 12 hour storage requirement to generate 80% of our energy from wind and solar [1], and weeks of storage for a 100% wind and solar grid. And remember, this is on top of the cost of actually generating all that energy in the first place. If people want to prove that these storage mechanisms are viable, then how about they build one minute's worth of storage. If we don't even have one minute's worth of storage provisioned, then I see zero reason to be confident in the ability to build hours, days, or weeks of storage.
By comparison, we'd need to build 9 nuclear plants for each one that presently exist to generate all of our electricity from nuclear. Any only 8 if we eliminate everything but nuclear and hydro. Also, It's 68 years since the first nuclear electrical plant and 80 years since the first fission reactor.
1. https://pv-magazine-usa.com/2018/03/01/12-hours-energy-stora...
Pumped hydro has always worked at scale.
You keep repeating that storage is not built out. We know. Before it can have been built out, it will need building out. But nukes are also not built out. Which can get done faster?
You just really wish storage tech was harder than it is because you need that for nukes not to look like the obviously bad investment they have proven, by "most of a century" of experience, to be.
By comparison, we need 6 to 7 orders of magnitude increase in our existing hydro and battery storage capacity to decarbonize through renewables. And an infinity order of magnitude increase in electrolysis storage, because we don't have any such storage at all. It's not that they haven't been built out. They haven't been built, full stop.
I don't need to make storage tech look any worse than it is. How much electrolysis storage capacity do we have, worldwide? Zero. I think you're the one engaging in wishful thinking, treating these totally unproven systems as certain when nobody has ever operated a grid storage electrolysis facility.
If someone told you they have plans for a supersonic passenger jet that will be even cheaper than normal airliners, would you believe them? If they actually had working planes, and they were actually able to build and operate a batch of a few dozen planes more cheaply than typical airlines then yes. But if they only had one plane, and little operational experience I wouldn't. And if all they had were plans on paper, I certainly would not - this is the stage that storage mechanisms other than hydro and batteries are in.
Pretending that "breakthroughs" will be needed to field storage must be your last hope, but building out storage is just construction. You will continue to be disappointed.
Come back to me when electrolysis storage systems are actually built, and we can examine the actual costs of storage the same way we examine the costs of nuclear: by looking at the bill after the plant has been built. If you really are so confident in their efficacy, then this should be no problem.
Today's thermal reactors, if they provided the entire 18 TW of primary energy demand, would consume in excess of 1 million tonnes of natural uranium per year. This would consume known uranium resources in less than a decade.
So, either seawater uranium would be needed (which would have to be scaled up by something like 11 orders of magnitude from what has been demonstrated) or breeder reactors would be needed (also not a proven technology, and likely more expensive than thermal burner reactors.)
The real figure [1] is 60,000 years worth of uranium with our current nuclear energy production, which is about 10% of our electrical demand. So 6,000 years for a 100% nuclear grid. Electricity production is about 25% of total energy demand, so call it 1,500 years for all energy converted to nuclear.
Furthermore, moving nuclear seawater extraction - even at it's present costs, without economies of scale - would not significantly impact nuclear's costs [2]:
> Fortunately, the cost of uranium is a small percentage of the cost of nuclear fuel, which is itself a small percentage of the cost of nuclear power. Over the last twenty years, uranium spot prices have varied between $10 and $120/lb of U3O8, mainly from changes in the availability of weapons-grade uranium to blend down to make reactor fuel.
> So as the cost of extracting U from seawater falls to below $100/lb, it will become a commercially viable alternative to mining new uranium ore. But even at $200/lb of U3O8, it doesn’t add more than a small fraction of a cent per kWh to the cost of nuclear power.
1. https://www.scientificamerican.com/article/how-long-will-glo...
2. https://www.forbes.com/sites/jamesconca/2016/07/01/uranium-s...
But deep subterranean cave and sub-ocean tanks for pumped hydro will be a thing. These make pumped hydro storage practical in radically more places than usually imagined. Combined with hill reservoirs, they multiply the storage capacity per unit mass of water.
A hilltop reservoir is, incidentally, an excellent place to site a solar array, which is cooled and more efficient by the water under it, and in turn radically reduces evaporative loss and biofouling in the reservoir.
We were originally planning to ditch domestic peat as fuel, in favor of Russian biofuel, but that's off the table now, and peat will probably be used extensively for a few years until alternatives are in place.
Energy independence is what we aim for at the moment. Carbon neutral is still something we aim for in the long run, but not being relianton Russian energy is the primary goal for the next few years.
For condos and apartment buildings by far the most common method of heating is district heating (teleheating) [1], and historically this has been very carbon intensive, even though cogeneration of both heat and electricity in one plant is quite efficient (efficiency > 80%; most Finnish thermal power plants are cogen). Fossil fuels and peat are being replaced with more sustainable (mostly wood-based) fuels, but attaining the emission goals requires burning less fuel, period, which means technologies like geothermal boreholes and large-scale heatpump facilities.
SMR nuclear reactors, if they ever become mainstream, would be an excellent source of clean heat and electricity for cities. Current nuclear power plants are located (by design) too far from cities for it to be economical to pipe their waste heat to where it's needed.
Its operating cost will necessarily be quite a bit more than solar, but it works in the Arctic winter, 24x7, and provides cogen heat.
It might end up cheaper to ship in ammonia synthesized from solar in the tropics. Most likely it will be a combination of several: normally, delivery by transmission line because cheapest, but with geothermal held ready for strategic backup, and stockpiled ammonia for load peaks.
Shipping will get cheaper as fuel does, but is already astonishingly cheap.
I’m not aware of any significant and serious efforts to replace ships with a green fuel, and they comprise a huge percentage of our emissions.
The west-African coastal Sahara, coastal Peru/Bolivia, Baja California, Arabia/Sudan/Eritrea, Yemen/Oman/Pakistan, Socotra, and north-western Australia all look like good places to site solar-driven ammonia synthesis. I don't doubt that less geographically-favored sites will dominate instead.
Some 42 million megawatts of energy reach the surface continually and are radiated into space as the earth cools from its initial molten state more than 4 billion years ago. No feasible amount of geothermal development could make even a small dent in this process. Furthermore, the earth’s heat budget is continually replenished by the radioactive decay of naturally occurring elements, and almost all of the energy associated with each decay event is converted to heat. Plus, the heat content of the geothermal reservoir rocks is continually replenished by conduction of heat from the earth’s deeper interior.
So a single nuclear power plant would be roughly equivalent to 0.002% of earths geothermal energy radiation. It doesn't sound like much, but for something as crucial as the earth's magnetic field, I wouldn't want to reduce it one bit.
I guess if the heat is radiated into space anyways and we simply capture that it doesn't speed up the core's energy loss, but if we start digging into the core and allowing energy to escape faster, we would effectively speed it up, right?
The radius of the Earth is 4000 miles. A 10-mile hole is thus 1/400 of the way to the center. You may as well worry that scratching the skin of an apple might damage the seeds.
Look at a graph of the temperature of the Earth as a function of depth. The temperature jumps tremendously below the crust, and is much more stable per depth below. The crust is the insulation of the Earth - and damaging that crust might affect the mantle is ways we cannot yet imagine.
The answer remains "we don't know".
The argument "it's big, we can't affect it" has been proven wrong in the case of the atmosphere, and again in the case of the ocean. It is no longer a sound argument.
Eruptions in Siberia, and later in India, not long ago geologically, released more heat in a (geologically) short time than we could use up in a million years, with no effect on the Earth's magnetic field.
I don't think we're even digging through the crust - there'd still be the mantle (~100x thicker) before we got to the core.
In numbers, I believe the deepest borehole is ~12km deep... and the Earth has a radius of >6000km. We're barely scratching the surface.
Since the layers are directly connected, it doesn't sound like to me that you'd have to dig into the very core for that to happen.
Of course at the current state of affairs the effects are miniscule, but it doesn't sound like a very good investment as something to potentially scale up in the future to where it will actually matter.
If it turns out to be a problem, how hard would it be to insert fuel back into the earth's core to sustain the magnetic field?
In another century, if we don't blast ourselves back to the stone age first (increasingly likely), energy from hydrogen-boron fusion will dominate wherever solar is impractical, and the geothermal wells will become too expensive to continue operating. So, either way, the whole process is an imperceptible blip.
Blasting our way back to the stone age will succeed in chopping off CO2 output suddenly, though. The climate could then return to normal in only a century or three, if the sudden change did not instead trigger an ice age or something.
You should worry instead about the effects of excreted pharmaceuticals and neo-nicotinoid pesticides on wildlife, excess fertilizer runoff on coastal ecosystems, and ocean acidification from CO2 dissolving to produce carbonic acid, making sea life unable to fix calcium for shells, destroying the underpinnings of the food chain and the whole ocean ecosystem. Oh, and global climate disruption.
We have no need to borrow imaginary trouble, we are making plenty of actually real trouble already.
I don't believe that waste heat is plenty. Here, in Romania, we use the waste heat from the nuclear power plant as district heating but that is enough for a small town near it.
You can have tiny heat pumps in every home that share a district-wide pipe as a heat source, you can use giant/deep heat pumps to supply the district-wide pipe and you can do both at the same time. And heat pumps can also be used to cool things, returning heat into the system and allowing for big solar gains in windows, since the heat generated can be re-used when it's more than needed rather than wasted.
This is still probably a good thing, but something to consider.
We have electricity run to almost everywhere there is a road, and every building that we spend any significant amount of time in. We can charge at work or on the street during the day. Basically anywhere a car is stationary.
With the right incentives and infrastructure we can shift electric vehicle charging to daytime, or whenever there is excess generating ability coming from the grid.
Because most people don't drive at night.
If a country has abundant solar power (probably not Finland!) it would make more sense to wire up workplace parking lots so that EVs could absorb the excess midday electricity.
That would be nighttime.
Some EVs can automatically charge at these times, and sometimes you get discounts for charging at these times, but you can also usually just set a timer on your charger.
https://www.oeb.ca/consumer-information-and-protection/elect...
For example the above suggests it's usually nighttime, but weekends and statutory holidays are also good.
As an aside, I wonder how much money an economy could save by having a new "cheap electricity holiday' which chooses one or two days a year that they announce a month in advance as national holidays when an extreme weather event is predicted.
It amazes me that we are still using steam power (mostly 18th and 19t century discovery AFAIR) in such advanced systems.
Predicting here there will be no fusion plants that drive steam turbines, ever. (Unless General Fusion's system turns out to work.)
There are projects working on these. They have much higher activation energy, so are harder to make happen -- for hydrogen-boron fusion, much, much harder. Helium-3 is scarce, effectively available only from decay of tritium, all of which has to be synthesized, then it needs to decay, with a half-life of 12 years.
Hydroelectric plants, nuclear reactors, gas and oil plants, all of them depend on mechanical movement.
https://www.youtube.com/watch?v=udJJ7n_Ryjg
With time renewables production will get less an less intermittent thanks to a more and more adequate spreading, to a mix (wind, solar...), to storage (hydrogen...) and an overly-expensive nuclear will become useless.
https://www.imperial.ac.uk/news/180592/european-cooperation-...
...if you continue to heat with gas, drive on petrol, fly on petroleum...
I don't want to be the party pooper but that renewable energy has to cover more than current electricity consumption does get overlooked continuously. Less by governments than by the media and general public, thankfully, but still.
But it is a lot of power.
And by the time you finally got those ten $10B plants online, Bitcoin's energy use would have ballooned to some even more absurd number, assuming we do nothing to stop the current trajectory.
To me, that’s a flaw of the charger if it keeps working when no device is connected.
As for TVs and others, we need to mandate a front-facing power switch, because most TVs/devices don’t have one anymore.
Have you ever worked at a big corporation? They pay for some stupid useless shit just because it’s nobody’s job to stop paying for the service.
and who's to judge it was useless? If you're the one paying, then you can make this judgement. Otherwise, you're merely putting your own moral values above someone else's.
If somebody was growing weed indoors, or they're smelting aluminium, then they're not wasting?
Edit: Found one myself: https://ccaf.io/cbeci/index/comparisons
Interestingly gold mining also uses more electricity than Bitcoin mining and that doesn't even include the associated costs of pollution, cleanups etc. Gold also isn't a network that can transfer value. On the other hand some of it is used in industrial applications.
Energy wasted by natural gas flaring is 5.5x more energy than bitcoin consumes. Renewable energy curtailment in China alone (turning generation off because we can't consume it fast enough) is almost enough energy on its own to power all bitcoin miners. https://ccaf.io/cbeci/index/comparisons
It's perfectly fine to have a negative opinion of bitcoin and proof of work, but you're wasting political capital in the fight against climate change when there are much bigger fish to fry against wasteful uses of energy that don't have an army of people, businesses, and even nation states (El Salvador) gearing up to fight you to defend their money.
reward in a currency for which you buy the energy. This takes into account the current btc/eur price in finland, if that's where you buy the energy, and that's not guaranteed to halve either.
But bitcoin is currently about a $1 trillion asset class, and growth of it's price has been slowly logarithmically for years. Most bullish cases suggest an eventual value of $10 trillion (in line with gold) to $100 trillion (in line with global bond market). But it's likely going to take decades (with several halving cycles) to get there.
Unless you're suggesting that it's likely to balloon in value even more and/or fast than that, I don't see mining ever becoming the biggest problem we have to deal with. Especially since bitcoin holders don't see PoW mining as a liability, but as a mission critical feature of the system.
https://web.archive.org/web/20130116000447/http://www.hs.fi/...
"Suomenkin uusi ydinvoimala maksaa 8.5 miljardia euroa" which translates to "Finland's new nuclear power plant will also cost 8.5 billion euros."
And let me be provocative (and probably downvoted here)... it also works during windless nights!
Luxembourg has 1/7th the population and could run off ONE of these.
The USA has 60x the population so would need about 420 of these?
at an average cost of $10 billion per plant, that's 4.2 trillion dollars. I think the US has spent more than that on the iraq war and the afganistan war - 8 trillion according to https://www.brown.edu/news/2021-09-01/costsofwar - which could've paid for these 420 plants twice over.
But US decided to invade Iraq and Afghanistan instead of any of those.
Okiluoto started in 2003 and was supposed to cost 3 Bns and be ready in 2009. it took 18 years instead of 6 and total cost is difficult to know exactly but is over 12 Bns instead of 3.
Building this plant (and the Flamanville one) put into light so many issues at so many levels that I am surprised it was completed and actually works.
Though the previously completed EPRs in Taishan was stopped since last june after gas leaks have been found in the primary circuit and framatome asked the US for help. Current talks point to a design flaw and the possibility of not restarting this EPRs is on the table. If this is confirmed, this flaw could also affect Okiluoto and flamanville EPRs.
With last winter trend of France finding design flaws in its reactors and being forced to stop them for emergency repairs and maintenance[1] (affecting the most recent and most powerful ones too), nuclear plant do not seems like a sound sustainable choice at least when France is involved.
[1]: https://www.ouest-france.fr/economie/entreprises/nucleaire-l...
The cynic in me would like to point out that it's not really running yet:
> Olkiluoto 3 started test production at just over 0.1 gigawatt, a small fraction of its capacity, with a ramp-up to full, regular electricity output planned by the end of July.
A /very small/ entire country of 5.5M.
By comparison, this wind turbine project near my parents was approved in 2016 and completed in 2018, providing 78 megawatts of power. Yes that's significantly less than the 1.6 gigawatts of this Finnish power plant. But, consider that in the same time period, 10 of this wind projects could be completed.
On top of that, solar projects are also much faster. Look at the Solar Star solar installation which provides .5 gigawatts of power, started in 2013 and completed in 2015. So 10 of these could have been completed in the same time as the Finnish system. No, I'm not suggesting that Solar is a good option in Finland. And yes, it would be important to work on massive battery storage systems, to make these work.
This just points out just how uneconomical nuclear power is. On top of that, with nuclear facilities coming under fire in Ukraine and Russia making (probably bluffing) threats against Finland, it really makes nuclear an unappealing option. Can someone point out why these projects are so attractive to so many people when it would appear that a combination of renewables appear to both be faster to bring on line and overall safer?
Edit: forgot the links,
Arkwright Summit https://en.wikipedia.org/wiki/Arkwright_Summit_Wind_Farm
Solar Star https://en.wikipedia.org/wiki/Solar_Star
There's also the aspect of "how much sun is there?"
https://en.wikipedia.org/wiki/Solar_energy_in_Finland
There are a number of issues with photovoltaic solar cells that close to the Arctic Circle.
What they need up there is a way to generate electricity from darkness.
Does this include the higher security needs around nuclear facilities?
I left out the construction costs, the Arkwright Summit farm, $125 million.
The Solar Star project was $2 billion.
This Finnish Nuclear site appears to have cost $12 billion.
That makes wind look really good, and solar at least on the same order (and still safer).
The other thing is the land. Solar and wind each need a substantial % of landmass to have 100% of our power come from those sources.
The ongoing costs of running nuclear are also way higher than solar or wind, which matters.
Significant public investment in wind energy announced to start construction in... 2026. That is a glacial pace in the face of an ecological and geopolitical crisis situation.
Reliability comes from solar and wind power redundancy and geographic distribution. If your collection area is over a few thousand square kilometres it is very rare for there to be no wind and no sun. Make it a few tens of thousand square kms (which modern high voltage transmission achieves) and your reliability is higher than coal.
That there is North Sea wind power, howsoever intermittent, is a pure good. Tying it into a larger network makes it better. The solution to local deficits is more localities.
Transmission lines are not expensive at all compared to nuclear power. This nuclear plant cost $12B and it is a cheap one!
Compare that to the SunCable is budgetted at $14B, (AU $20B in the article = US$20B) which is an undersea(!) HVAC cable all the way from Australia to Singapore (3,800km!) AND a 3GW(!) solar farm[1].
By comparison, the distance from Spain to Scotland is 2400km. And when the wind stopped in the North Sea, Spain was setting records in terms of the amount of power generated from wind farms[2]
[1] https://www.intelligentliving.co/australian-undersea-sun-cab...
[2] https://www.evwind.es/2021/12/03/27-8-of-electricity-came-fr...
It does insofar as it matters for capital. Who wants to invest in a plant that will take at least ten years (but probably more with cost overruns in the billions) before they see a ROI? Especially when the cost per MWH from a renewable project that will be online in 2 years with less risk is already comparable if not more competitive.
you gotta compare like-for-like. If the solar project that takes 2 years only provide power half the time, then you need double the size to provide the same amortized level of power at night. You also need some form of storage. And that's if you don't have a spate of bad weather preventing it from working - so to amortize that problem you'd need to build yet larger...
To answer more directly though, yeah the power is the same cost. Perhaps when renewable penetration into the energy market is saturated, there will be a greater demand for base load at all those times renewables aren't producing at peak, and that will be reflected in those nuclear MWHs becoming very profitable even at a higher unit cost.
It's mostly (>60%) a mix of solar and wind power, with some gas that fills in the gaps - as well as batteries for grid stability. Still importing some coal power from interstate, but that is decreasing too.
The investment has been incremental - so much smaller amounts, with much less risk and therefor more attractive to investors.
A large part of this (since 2018) has been done by a conservative state government, who have been highly supportive of the renewable transition.
https://theconversation.com/against-the-odds-south-australia...
I would absolutely never invest in a nuclear project but I sure am glad they are there to keep the lights on when the weather doesn’t cooperate for wind and solar.
A mix of different sources is the key to a robust grid, and nuclear is a great part of that mix.
As a side note on British Columbia site C 1000 MW a hydro dam is currently looking like it will cost 16 billion and take about 10 years to build, those numbers could easily be for a nuclear plant.
Markets are interesting for economic dispatch based on marginal cost, but then real world constraints such as rivers that must flow and a lack of infinite transmission capacity in all directions kick in and it starts to look a lot like what it replaced. I guess it works where it works
Who wants to invest in a plant that will take at least ten years
This points out one of the sad flaws of the human race and ultimately, it's probably the one that will lead to our downfall.We're absolute crap at thinking long-term.
Look at you, talking about ten years as if it's eons. You're not wrong, of course! Capital doesn't like to invest in projects ten+ years before ROI.
But ten years is not a long time. We should be thinking about many, many things at least ten years in the future. Hell, forget ten years. We should be plotting our energy strategy with an eye to the next hundreds of years.
Of course, we won't, because we're humans and we really struggle to think past next week. And those of us in democracies have designed a system that literally punishes politicians for thinking beyond the next election cycle.
Who in 2000 would have guessed solar and wind would be radically cheaper than coal? No 100-year plan would have mentioned them.
If small-scale hydrogen-boron aneutronic fusion becomes unexpectedly practical in 20 years, all the other plans go out the window.
The worst case of nuclear, it is worse than the worst case of solar/wind. So even if it were rational for humanity, it might not be rational for a country.
I'm having trouble picturing how it is safer than solar though.
https://www.nextbigfuture.com/2008/03/deaths-per-twh-for-all...
Nuclear takes longer, is more expensive, has lower ROI, and higher risks. Solar has a lower capacity factor, but having 1/3 the availability at 1/15th the cost is a net win. Especially as we need vastly more power in the daytime and idling Nuclear is really expensive.
Currently 3% of global electricity comes from Solar and 16% from hydro with Nuclear only proving 10%. Scaling Nuclear to a significantly on a global scale take not just massive construction and new regulations, but also training etc, we simply don’t have the time.
“Nuclear Energy consuming roughly 400 gallons of water per megawatt-hour, 320 billion gallons of water were consumed by United States nuclear power plant electricity generation in 2015.” And that’s direct consumption in cooling towers, nuclear indirectly uses power in other ways.
By comparison the 550-megawatt Desert Sunlight project in Riverside County estimated 2/3 cup of water per megawatt hour.
The notion that nuclear power is going to significant affect water supplies is without merit.
1. http://large.stanford.edu/courses/2017/ph241/styles2/#:~:tex....
2. http://large.stanford.edu/courses/2017/ph241/styles2/images/...
3. https://en.wikipedia.org/wiki/Palo_Verde_Nuclear_Generating_...
However, wastewater is just water. Look at a long river and towns upstream dump their wastewater into rivers that towns and cities downstream collect as municipal water.
1. https://www.statista.com/statistics/494425/death-rate-worldw...
Which is misleading in several ways, both because it ignores the majority of solar power and ignores how safe that power will be over time.
Nuke fuel cost is huge compared to operating cost of solar and wind.
Essentially, building a nuclear power plant in 2022 means you are betting we won't have workable storage for renewables by 2052.
If you add in batteries with todays technology the nuclear plants are competituve with solar or wind.
So the alternative is coal or natural gas plants. Which then have their own drawbacks.
Solutions that are built today need to use technology available today.
Nuclear is fine, especially when you are not buying the first reactor of its kind from a vendor who has never fully built a plant on its own. Areva got a tad too greedy and cut out the middleman in the form of doing 100% of the work themselves instead of the usual 30% and contracting out the rest. They ware not helped by the fameously strict Finnish regulatory authority (STUK).
Add that in and the equation looks substantially different.
Nuclear power plants produce maximum power 92.5% of the time. Compare that to other energy sources:
- Geothermal: 74.3%
- Nat gas: 56.6%
- Hydropower: 41.5%
- Coal: 40.2%
- Wind: 35.4%
- Solar: 24.9%
Batteries are a joke. Consider the 409MW / 900MWh battery at Florida Power & Light: this is only enough to power 329,000 homes just over two hours. What happens after the juice runs out? In a day the RE Ginna Nuclear Plant in New York operates at 582 MW--in 24 hours thats 13,968MWh guaranteed! [3] That's powering over 329,000 or more homes without fear of outages. Battery systems in conjunction with renewables brings the capital cost per kwh of nuclear vs renewable to closer to 2:1 (6k $/kW vs 3k $/kW) too. So you're essentially getting 3x the reliability for 2x the cost when using nuclear and outages that exceed a few hours are a non issue. [4]
[1]: https://www.energy.gov/ne/articles/nuclear-power-most-reliab...
[2]: https://www.energy-storage.news/worlds-biggest-solar-charged...
[3]: https://www.eia.gov/tools/faqs/faq.php?id=104&t=3
[4]: https://www.eia.gov/analysis/studies/powerplants/capitalcost... page 28
Energy prices can be negative when there's not enough load but too much supply. Not every power source can be just switched off.
The person I responded to claimed that nuclear plants run at close to 100% because they bid low because the marginal cost of their electricity production is low, but the same is true for renewables like wind and solar. Yet these renewables run at much lower utilization rates - because of weather and daylight cycle, not "because they can", except in rare cases of negative prices as you mentioned.
Which seems to topple most of your argument.
As for wind turbines on land, they require a lot more space for the same yield, space which is stolen or irreversibly destroyed for the local fauna. Here in Norway, wind turbines near settlements are also forced to run on diminished capacity at night because of the health problems people associate with the 24/7 humming and whoosh noises (not kidding).
Funnily enough, the 2nd and 3rd EPRs in China both opened before this one, taking "only" 9 years from start to production. They're also the world's largest reactors now.
One of them is shut down since mid-2021 after an incident (leak).
To produce 1 gigawatt of power you need 1000 square kilometers of wind turbines or 300 sq km of solar elements or 3 sq km of nuclear power plants. How much land do you have in your country that you are ready to deforestate in order to build renewables?
Predictability.
Renewables depend on weather. They only work when the wind blows or the sun shines. Are you ready to be able to heat your house only when the weather forecast is good?
On top of that, some solar installations are actually compatible with some foods, here's one article on that: https://www.dw.com/en/farmers-reap-double-benefits-with-sola...
Point being, land use doesn't need to be single purpose in your example.
In terms of the weather, this is why it important to have balanced installations and associated battery storage.
There is absolutely no need for single-use solar or wind area, anywhere.
Predictability: spreading out production units, using a mix (wind, solar...) and storage are key. https://www.imperial.ac.uk/news/180592/european-cooperation-...
https://www.npr.org/2022/03/11/1085427380/ukraine-nuclear-po...
1. Bad management of construction project, almost near corruption level stupidity. Many constructions tasks outsourced to contractors who outsourced them to contractors who outsourced them to contractors, making it easy to take "cost-saving" shortcuts and difficult to supervise.
2. Failure of corruption to speed things up: Finnish nuclear safety authorities are not easily bribed, so when issues with bad quality of welds, concrete, boiler valves and safety electronics were identified (all this from memory, these were separate incidents), the issues could not be smoothed over and ignored with well-placed thick envelopes. The authorities would demand the construction crew to tear stuff apart and do again, properly. And if it didn't pass, then again. And again.
Most of the issues I have read about do not sound like "nuclear technology" failures, more about failures in building a big pressurized boiler power plant. The nuclear part comes in by authorities requiring high quality. They couldn't make good enough concrete bed on a first try, that isn't some super novel space technology.
It mostly reminds me of similar kind of mismanagement that plagues many big construction projects run by big corps managed by suits. During same time frame city of Helsinki wasted amazing amount of money in a "automated metro car" subway upgrade project they bought from Siemens, which ultimately didn't work and had to be scrapped.
(edit. City of Helsinki decided to "automate" city subway metro system in 2006, contract signed with Siemens in 2008, originally planned to be completed in 2011. Project was postponed several times and effectively scrapped in 2016. Tried googling most recent news, the lower district court had given judgement in 2021, parties likely to appeal.)
Other forms of generation that require GHG-emitting backup generation.
https://en.wikipedia.org/wiki/Yucca_Mountain_nuclear_waste_r...
The method is Swedish, they seem to have good pictures of it here: https://www.skb.com/future-projects/the-spent-fuel-repositor...
And it's a fraction of the price of nuclear.
Renewables are usually cheaper per W, but way more expensive in real world usage (battery storage + full life cycle costs)
The area around Finland and Eastern Europe is one of the worst in the world for renewables, though.
But yeah, neither are the Swedish river valleys (so far).
If yes, they should do that. If no, they should take the website down and stop misleading people.
The only climate compatible way is not an alternative on demande source of energy, but the other way around: adapt our energy consumption to its availability and significantly lower our energy use. (see this 2009 piece by low tech magazine[1])
This is the real issue with dealing with climate change: we have to drastically change our way of living, in ways that most of us have not properly grasped and are not ok with.
But it is not a matter of choice, this will happen. It is a matter of choosing to do it in a somewhat controlled manner over the few time left, of to be subjected to this change in a brutal way.
[1]: https://solar.lowtechmagazine.com/2009/11/renewable-energy-i...
We need energy equivalent of grains: renewable and storable.
But defects were found that would jeopardize the current evaluation to renew the certification for using them for 10 more years, so the decision was made to stop several reactors for forced maintenance and repairs.
https://www.sciencedirect.com/science/article/abs/pii/S03014...
Any newly built renewable generation should be used to retire fossil fuel plants first, and once those are gone then we can consider retiring (current) nuclear.
Yes there are unremplacable parts in a nuclear reactor, but if it's measured to be safe to continue, then there is no reason to respect the initial EOL.
Fukushima Daini did not have those problems, and thus not much drama happened at it:
* https://www.researchgate.net/figure/Comparison-of-flood-dama...
* https://hbr.org/2014/07/how-the-other-fukushima-plant-surviv...
The two plants are 12 km apart and got hit with the same tsunami.
https://en.wikipedia.org/wiki/Beznau_Nuclear_Power_Plant
In don't know the situation in all of Europe, but there could be potential to buy us quite of lot of time to really ramp up alternatives.
You'd need huge amounts of capital with big risks and little profits foreseen. The track record from the latest western projects is horrible so I don't see how it would be possible to get the backing now.
Your implication is "cut corners" which is a misunderstanding.
Ok, so nationalize it. Problem solved.
> In November 2012 it was discovered that over 5,000 small components used in five reactors at Yeonggwang Nuclear Power Plant had not been properly certified; eight suppliers had faked 60 warranties for the parts. Two reactors were shut down for component replacement, which was likely to cause power shortages in South Korea during the winter.[23] Reuters reported this as South Korea's worst nuclear crisis, highlighting a lack of transparency on nuclear safety and the dual roles of South Korea's nuclear regulators on supervision and promotion.[24] This incident followed the prosecution of five senior engineers for the coverup of a serious loss of power and cooling incident at Kori Nuclear Power Plant, which was subsequently graded at INES level 2.[23][25]
> In 2013, there was a scandal involving the use of counterfeit parts in nuclear plants and faked quality assurance certificates. In June 2013 Kori 2 and Shin Wolsong 1 were shut down, and Kori 1 and Shin Wolsong 2 ordered to remain offline, until safety-related control cabling with forged safety certificates is replaced.[26] Control cabling in the first APR-1400s under construction had to be replaced delaying construction by up to a year.[27] In October 2013 about 100 people were indicted for falsifying safety documents, including a former chief executive of Korea Hydro & Nuclear Power and a vice-president of Korea Electric Power Corporation.[28]
https://en.m.wikipedia.org/wiki/Nuclear_power_in_South_Korea
I'm curious how many scandals are involved with similar projects taking twice as long to complete in Europe. Or projects taking 4 times as long to complete in the USA? Fewer scandals? More scandals? Worse scandals? I have no idea.
https://reporterre.net/Stress-peur-pression-le-difficile-quo...
Even if we reach 0 in 13 years, the road to flipping the magnitude will be long, and I estimate longer than the time to build a reactor.
We had this "too slow to build" -argument 15 years ago, but no other renewables have delivered. We built 67 new windmills in 2020. That number would have to be double for your argument to start being plausible in our environment.
France has 56 nuclear plants that provide roughly 73% of the energy needs of the country. ~73% of this capacity was finished between 1980 and 1990.
Modern regulation and the scarcity of new builds has made building slower, but it should be expected that Areva, the builder of Olkiluoto 3, should be able to pump out new facilities and significantly faster rate compared to the last decade.
These nuclear plants haven't delivered. Meanwhile, renewables have become cheap and mainstream, and their market keeps improving constantly.
> Areva, the builder of Olkiluoto 3, should be able to pump out new facilities and significantly faster rate compared to the last decade.
They should but do they? I hear it's not going so well in their new project in the UK either.
https://www.ge.com/renewableenergy/wind-energy/offshore-wind...
https://www.vestas.com/en/products/offshore/V236-15MW
> Modern regulation and the scarcity of new builds has made building slower, but it should be expected that Areva, the builder of Olkiluoto 3, should be able to pump out new facilities and significantly faster rate compared to the last decade.
Went so swimmingly that Areva went into bankruptcy a couple of years ago. The company only exists to shield EDF and the French state from any remaining risk they still can from Olkilouto 3.
He basically says that France is currently or close to be facing a industrial failure for the whole existing nuclear plants which means the nuclear safety cannot be guaranteed. The ability to build anything nuclear is out of reach for France who lacks engineers and technical know how which is the consequences of decades old political decisions to outsource to China, there is a lack of anticipation and no plans which is leading France in a probable dead-end.
The current French EPR in flamanville has confirmed what happened with Okiluoto, hundreds of failures, lack of planning, huge delays, low quality with forged document, going over budget by several times.
You may be interested in reading Marc Endeweld most recent book "L'Emprise. La France sous influence" it covers the current state of nuclear in France and it depicts an even bleaker picture than what the head of ASN publicly acknowledges.
[1]: https://www.lemonde.fr/economie/article/2022/01/19/la-poursu...
https://ourworldindata.org/grapher/nuclear-renewables-electr...
You can see that the total share of renewables has climbed significantly, but production is heavily weighted on summer months when there is no shortage of electricity. https://ourworldindata.org/grapher/nuclear-renewables-electr...
These numbers are all insignificant, tho. Finland needs to build roughly 22-35GW of renewable/nuclear power to get rid of carbon based energy, and we're nowhere near.
The clear answer is that we need both wind and nuclear – a LOT of both, but I doubt we'll do neither in sufficient quantity.
Understood, thank you!
More minor points:
> You'd need to build 1300+ 3MW wind turbines
Modern offshore ones develop 12MW, and their load factor peaks at .6
> We had this "too slow to build" -argument 15 years ago, but no other renewables have delivered.
Nuclear isn't a renewable source.
Reactors take 5-10 years to build.
South Korea is good place to learn from
Also we already have a similar level of wrongdoings with the French EPRs.
You also don't seem to realize the other reason, and the primary reason, to lockdown is to lighten the peak load on hospitals, in response to waves of infection.
Finland has another nuclear power plant under construction as well... or at least we did, until the war started, now I don't know what will happen. Rusatom was supposed to supply the reactor for Hanhikivi nuclear power plant, which was also severely delayed.
Russia is also an important supplier of nuclear fuel to Finland.
The electricity prices are through the roof for other reasons (and have been for almost a year now) and are not related to Russia at all.
I have to do some reading, but my understanding was that the Finnish plant is using an alternate funding structure from many of the existing nuclear installations. Less direct subsidies or more risk directly on the commercial entities?
Simply put, Sweden and Norway share the Scandinavian mountain ridge which gives a lot of rain at altitude and dammable valleys; Finland is on the whole much flatter, so has less favourable conditions for hydro power.
> I have to do some reading, but my understanding was that the Finnish plant is using an alternate funding structure from many of the existing nuclear installations. Less direct subsidies or more risk directly on the commercial entities?
Haven't checked recently, but at a guess / from vague memory: Probably shoving off as much as possible of the financing onto the builder / owner, Rosatom (mainly via its Finnish "partners" / subsidiaries), but in the end backed up by State guarantees because who else would voluntarily/ is big enough. All of course dressed up in more or less convoluted arrangements as suitable to make it look a little better / less bad.
(What, me cynical?)
Yeah, I had Quebec in mind as a similar geography without the large mountains of the Rockies and Cascades. I didn't account for just how flat Finland is, and how high a big chunk of Quebec is. Interestingly at first they appeared similar, the high points are quite close. But looking at elevation profiles it was clear how misleading that can be.
It looks like I was a bit mixed up, the structure I was thinking of is called the Finnish Mankala system. Energy producers are owned by parties that bear the costs of operating the company. Owners receive shares of electricity at cost, any unwanted portion is sold by them into the Nordic market. This means that output is effectively contracted to each owner over the life of the plant. The private owners are mostly heavy industry with a high demand for base-load power, and hence low costs are critical for them.
FWIW the plant construction appears to be a fixed price contract with a consortium of plant suppliers: AREVA GmbH, AREVA NP SAS and Siemens AG, which are jointly liable for the obligations under the plant supply contract until the end of the plant unit's warranty period.
Correct!
> are not related to Russia at all.
Wrong!
The price increase has EVERYTHING to do with Russia... because the conflict has been ongoing for much longer: https://news.ycombinator.com/item?id=30522164
Those trading energy knew of the energy related tensions between Russia and the west and hence were bidding high prices for these commidities in the futures markets.
https://www.newcivilengineer.com/latest/rolls-royce-submits-...
Not 24/7.
Political, because it should already be banned.
https://www.world-nuclear.org/information-library/country-pr...
still cleaning up mess at ranger (which has impacted on a dual-listed world heritage national park) and rum jungle (there's a class action of the few surviving workers + their families whose cohort have suffered cancers)
notably still operating is olympic dam, where the huge volumes of radioactive tailings literally spill out on the surrounding land, representing an entirely unmanaged environmental hazard.
uranium mining is unclean unsafe and unwanted
For wind, we're too small country - there are always days without any wind. There are even days without any wind in nearby countries included.
and in every place connected by water to Fukushima.
That's the reason it has struggled for traction.
It is the first nuclear reactor in Europe for 15 years so not much working experience or available sub contractors.
Apparently, China, South Korea, Japan and Russia can build at a third of the cost and time of that.
If nuclear energy should be considered, much more must be built more continuously.
> Apparently, China, South Korea, Japan and Russia can build at a third of the cost and time of that.
Any insight into the why?China in particular plans to build ~250 new reactors over the next few years, most like new HTG reactors based on the pebble bed technology Germany sold to them when they abandoned their next-gen nuclear plans.
Russia has reactor building capabilities that are still current but their domestic needs are stagnating so said capability could decay as they don't actually need to build modern reactors at this time.
Japan has a similar problem to Russia in that post-Fukishima there isn't domestic demand for nuclear reactors. However they are building reactors for other countries, in particular I think they are planning to build ~20 good sized reactors in India.
It would be more honest to cite the much smaller number that have actually broken ground. Nobody knows how many of those will be completed, or how many of those completed will be fueled or operated continuously, or where operated actually mainly generate power, as opposed to generating plutonium and tritium for weapons.
What do you mean there isn't enough fuel? Not enough pellets/pebbles? Well ofcourse.. there is only 2 operational reactors right now... not enough uranium? Yeah no. There is way more than enough uranium to fuel their projected fleet and it's not like they are building it tomorrow, it's probably going to take until around 2050 to complete.
China has a track record of saying they will do something and then actually doing it, I'm inclined to believe they will make good on that number.
I get that people don't like China but lets be serious, no-one else is actually as serious about nuclear power as them right now.
Any organization as big as the Chinese gov't makes lots of plans, and changes them as conditions change. It is one thing to be prepared to build a lot of nukes, entirely another to start building them, and entirely a third to finish them. The last will depend on conditions in the world, and of political alliances at the time.
And regret about it? The French are in much better position compared to the German with that low-cost power enthusiasm yet still heavily dependent on burning fossil.
My current feeling is that if they stick to their plan and build these smaller 600MW reactors that can mostly be built in factories and assembled on-site it's going to be a vastly different economic proposition than existing "big nuclear" that has been attempted in the West.
Of course there is no way to know exactly how it plays out but the inputs look good.
The source is a Bloomberg article ( https://www.bloomberg.com/news/features/2021-11-02/china-cli... ) which states that the boss of Chine General Power corp. announced his plans 200GW for 2035, nothing more. Admitting that it is an official governmental announcement (it doesn't seem so(?)) and given that China already has 50GW, that's maybe 100GW new (way less than 150 standard reactors).
Compare with renewables: 790GW already running (26% of the gridpower), and 1200GW planned for 2030. In 2020 China added 71,6GW windturbine power. Even considering the load factors the picture is pretty clear.
China has been constructing a lot of new nuclear power plants over the last 15 years -- estimated at ~12 GW in 2013, but now closer to 50 GW as of 2021. Wikipedia says 50 plants as of 2021: https://en.wikipedia.org/wiki/Nuclear_power_in_China.
Anecdotally I've heard that temporary pollution control measures during the 2008 olympics gave the populace and decision makers a taste of reduced air pollution, and gave increased political willpower to invest in solar, wind, and nuclear power generation.
* The overall design must be done before construction starts, also no room for regulatory changes. Waterfall is better than Agile for nuclear.
* Experienced project management, work force and supply chain.
* Build many reactors on the same site and don't use a new reactor design.
* Work force is overall cheaper and possibly also more productive in Asia.
More or less the same as for everything else, the more you do it the better and cheaper it gets but it requires a lot of upfront costs.
This isn't new; historically, the first couple of examples of any given nuclear power plant design have typically seen major overruns.
> Any insight into the why?
At least as for China, one gets the feeling (from recent news about COVID-19 hospitals being built in a week, the world's largest dam in a few years, etc) that with a population of over a billion, they do it Pharaonic Egypt pyramid-building style: Throw a few thousand engineers and a few hundred thousand construction workers at anything, and you will get something built.
Nuclear is just too big for a privatized energy market’s participants.
Sadly NuScale seems to be struggling to meet timeline and cost targets, and there were some headlines last year about the sponsoring utility pulling out of the project. I'm rooting for them but it doesn't look good.
The RR project is still just on paper really, and is closer to a medium sized reactor than SMR. Maybe they've cracked the code? Maybe not, we'll see.
Every nuclear thread here people chime in with a reflexive "just build nuclear smarter" answer without actually addressing why every prior attempt at this has failed. A lot of people don't want to develop an understanding of the challenges more sophisticated than smugly blaming environmental activists, over regulation, etc.
Look at these projects from the prospective of potential private investment. Anyone doing basic due diligence is going to realize that the odds are stacked against a project hitting it's time and cost goals. Then you look at the trend lines for levelized cost of renewables + storage, and you realize that even in the best case scenario, within 2 decades you may be squeezed out of the market even if the efficiencies of scale and learning kick in.
For me even seeing the Tesla Berlin factory delays makes me sad: in China already the second factory is being built while Germany is coming up with new arguments without looking at the cost/benefit ratio for EU of those delays.
https://www.sciencedirect.com/science/article/abs/pii/S03014...
There's huge huge risk in choosing a particular design and building even one of it, because we don't know if it will be constructible the first time, and we don't know if future builds of the first design will be more or less expensive.
When each build is a $10B roll of the dice with variance of 2-3x of initial estimates, it's a bit difficult to find rational financial backers. Especially when there's not that much profit to be had from even a successful build. The risk reward is completely out of whack compared to the other options for carbon neutral energy.
Far too many people are generalizing from the French and American nuclear programs, both of which built lots of reactors in a comparatively short time and then were fear-mongered into a standstill by the fossil fuel lobby.
https://www.sciencedirect.com/science/article/pii/S030142151...
"""In the third era of nuclear power construction in Japan, from 1980 to 2007, costs remain between ¥250,000/kW and ¥400,000/kW, representing an annual change of −1% to 1%. This period experienced relatively stable costs over 27 years."""
It would be great to see an attempt to such battery solution that would cover the same amount of capacity as this plant, that can operate for at least several months without recharging, in Finish winter, and cost less than this plant and be built faster. That would check all the boxes, and if such technology already exist, people here should really put their investment money into it.
1970s nuclear safety standards, despite it all, were still better than the energy strategy the world adopted from 1970-2020. Killing off nuclear in search of a perfect power system was a stupid strategy, and failed. The only unfortunate point of karmic justice is that Europe ended up reliant on Russian gas and in an energy crisis as a reward for their stubbornness against making the technically obvious choice.
Well done Finland for even managing to get a reactor built in the face of all that.
If they'd acted rationally, acknowledged Fukushima and moved on with trying to make their nuclear power cheaper instead letting ideology determine that part of their energy policy then they wouldn't be in the mess they are in. Instead they pushed ahead with renewables, ignored technical problems like reliability and have ended up looking like fools while literally paying a high price for the privilege. France continues to quietly plod away as a reliable European energy success story.
In France nuke-power is backed by gas (which produced 7.5% of the gridpower in 2020).
The sole reactor currently planned (Flamanville-3) is a complete disaster, more than 12 years behind schedule, it will cost at least 19.4 billion € (initial budget: 3.7 billion €).
Maybe you have some actual knowledge, but I have never found somebody who says that regulations are the problem but has any concrete suggestions for changing regulations. It's just a vague gut feeling. And in the case of France I doubt it applies at all.
Construction is not like manufacturing, it does not see continual productivity improvements like manufacturing does:
https://www.nist.gov/publications/measuring-and-improving-us...
As an energy source whose costs are primarily construction related, we would not expect to see it falling in cost over time. We would expect that energy sources whose costs are dominated by manufacturing to outcompete nuclear as time passes.
I don't think there is any reason to think it will be different for future ones if any. We'll see what happens for the British one (Hinkley Point C), but they already know there will be large delays and cost overrun.
Yup, exactly: And then there is a huge stink about this and no more are built for a good while, so the next one is a first one again. Over and over and over. Lather, rinse, repeat, repeat, repeat, repeat...
https://en.m.wikipedia.org/wiki/Olkiluoto_Nuclear_Power_Plan...
When did Japan last build a nuclear reactor? I don't think any time recently.
South Korea used to be touted as a success at construction without massive overruns, but it turns out that it was largely a result or corruption and skimping on safety inspections:
https://www.straitstimes.com/asia/s-korea-jails-nuclear-work...
As for China and Russia, we don't really have much insight to what they are doing as far as safety. China is seems to be successful at large scale construction projects in a way that we can not replicate in the west, so perhaps their numbers are reasonable for construction costs.
> If nuclear energy should be considered, much more must be built more continuously.
We would need entirely new designs unlike what has been built in the past. Both France and the US have negative learning rates when building the same reactor design multiple times, and that was 50 years ago when construction was a much more effective part of our economies.
I do not believe that nuclear is a smart energy source to pursue given our modern production capabilities. There's a bevy of nuclear startups trying smaller reactors that might be able to constrain construction costs. But in the past these designs have been rejected because of the loss of economy of scale, as being too expensive per watt.
Of the potential carbon neutral energy sources of the future, nuclear is one of the e least practical. It may supply a tiny fraction of our future power, maybe 10%, but without a major revolution soon on construction, our aging reactors will be shut down at end of life without any way to build more of them.
Are they? Considering that their population is higher than the whole of North America + EU + Russia combined, wouldn't it be fair to compare it that way? Sure, it's one country as opposed to several, but still, the population plays a huge role in this "amazing construction at scale".
seems to me other factors like economics and government structure are more important, don't think a 4x larger US would be building faster and more cheaply
I'd say it's more fair to compare it to a region of equal population. People actually do stuff, and the more of them (especially educated ones) there are, the more stuff will get done.
People are the biggest resource these days, which western countries realized a long time ago (or maybe it's the other way around, western countries created this system?). Hence, immigration heavily in favour of the best from other parts of the world.
And higher concentrations of people are more productive and effective. Think cities vs rural areas.
After accounting for that and comparing, if your region (clump of people) is still losing, then you might have a real problem and should take notes from the other group.
I agree that a gigantic shift is required and put my hopes into mass produced SMRs. It's gonna take time and money, yes, just like the shift to EVs and renewables.
Fossil fuels is still above 80% of global primary energy, nuclear 5% and renewables excluding hydro 2%.
I really don't think putting all eggs in the solar/wind basket is good. They should of course also get heavy investments but that doesn't have to exclude nuclear. We're gonna need everything we have to end the fossil era.
Even in the first nuclear build out in the US, large cost overruns were very common. Forbes magazine was famously critical of this in a 1985 cover article.
There's a reason the US stopped building NPPs back then and it wasn't green mind control.
Rest was covered by Areva, since the cost overruns were of their own failure.
It took over 4 times as long to built as pitched, and over 3 times as expensive.
Everyone doing comparison calculations with renewables, remember that.
Germany had spectacular delays and overruns for a new airport for Berlin That too doesn't mean Europe forgot how to build airports.
This is also the nuclear plant (Taishan) that was in the news last year regarding damaged fuel rods.
That's the output from the experts in France so far.
Areva was basically shuttered and written off as a loss during all this. A part of the company only still exists as part of this Finland deal.
e.g. Depending on whose point of view you read, solar/wind prices either includes or not: subsidies, storage, land, weather, green label costs passed on to customers, interest rates, etc. Coal prices either includes or not: labor, imports, duties, mining, environmental costs, health costs, etc.
Lately I've come to a conclusion that we can make any of these methods appear equal, higher or lower by shifting the books.
Atleast I'm happy that this article is focusing only on the benefits and outcome, rather than invent winners and losers.
What do power execs care if they leave behind ruins decades down the road? They will have already made their money and enjoyed it.
It's depressing to think there's a growing army of geeks who have given up on science, rationality and objective reality just because they got sucked in by some propaganda and tied their identity a bit too firmly to it to ever escape.
Politics and the funding of state actions seems to be enacted highly subjectively according to power plays and vested interests, with minimal impact from rational geeks.
This is the defining issue of our times in my opinion, the reason climate change is the barely mitigated disaster it's turning into.
We only get a small fraction of the possible benefits of science as a race, because so much of our potential is wasted or actively worked against.
But literally every reactor ever built depended more on government extraction and concentration of capital (i.e., politics) than on market forces, making it all even less predictable.
But maybe if remotely applicable, an optimistic view can be: that some of those geeks, some of the times care about seeing progress happen, rather than the means.
Throwing your hands up and declaring the whole thing unknowable just because (I assume) the expert consensus is coming up with a different answer than you were confidently told and believed about renewables for decades by talking heads in your media bubble seems a weak cop out.
Either prove to everyone that it's a big conspiracy and you were right all along, or convince yourself that what you were told previously was a big conspiracy. One of these options is true.
I think you should read the thread and context of the reply again.
Just to make the misunderstanding clear: Any *green energy* that takes us out of coal/peat/oil is progress. You don't have to repeat as if there is a conspiracy. I was replying to a comment asking for comparison with other sources, saying that *progress to green energy is way more important* than comparisons against brown energy, no matter even if said comparisons paint coal/peat/oil in favourable or unfavorable terms. It's exactly the same you said, burning peat doesn't make sense today no matter the cost, and that's exactly the same I'm saying.
Areva/Orano being a french state owned (mostly) company, this is probably largely paid for by the French tax payer.
Also, Areva is French and Siemens hasn't held any shares in the company since 2009.
In Finland nuclear is the only option. Happy to see it come online.
Now that I think of it, I've never anyone speak of the impact on wildlife, nor seen a wind turbine in a forest (only ever on open farmland). Considering both noise and large shadows moving constantly, I assume it will have some impact. (I did hear that bird strikes are a non-issue in relative terms.) Even Wikipedia has no info on anything but birds/bats for on-shore installations https://en.wikipedia.org/wiki/Environmental_impact_of_wind_p...
Edit: double checked that Finland is actually mostly forest: [PDF] https://www.eea.europa.eu/themes/landuse/land-cover-country-... Screenshot from relevant part of PDF: https://snipboard.io/KFDEIr.jpg
The 9+5+4=18% water bodies, arable land, and pastures/mosaics (respectively) might also be a good target.
https://en.wikipedia.org/wiki/Surface_power_density says 1.84 W/m², so at 18% of 338'662 "hundreds ha" = 61 billion m² you get 112 GW which translates into 983 TWh after a year (8760 hours). Looking at https://en.wikipedia.org/wiki/Energy_in_Finland that's 2.6 times more energy than they used in 2013 (this includes heating, driving, etc. but not things like imported clothes, plastic products, etc.). All this is considering only the land area, not sea.
Future work: calculate how many years of monopolizing the world's steel production it takes to get these things produced, much less built in the middle of nowhere with frozen winters.
1) wind moves faster/freer the higher you are above the ground. the height of the trees moves the ‘ground’ up, without actually moving it up from a foundation or structure perspective. So you spend the money for a 300 ft tower, but only get 200ft of usable height. Not fun.
2) trees grow into things, fall on things, burn at inconvenient times, and are generally a maintenance headache.
3) many types of trees are very, very strong and require expensive heavy equipment to clear at large scales, especially if you need to remove a lot of stumps. So it adds extra cost above some already significant costs of land.
If you already have some cleared land somewhere, assuming all other factors are equal, it will definitely be preferred.
If the only land they have is trees, it does restrict the options quite a bit. I also forgot to mention, in most climates trees are a hassle this way, they also grow naturally, so even if you clear the land you need to go back and keep it clear every couple years.
Solar has similar drawbacks but worse - you can’t just clear the trees around where you’d put the windmills and roads, you’d need to clear pretty much everywhere including from where they would shade the panels. Which greatly increases the footprint.
Trees can of course be burned for heat and energy, but it’s a time consuming, dangerous, and inefficient process (time/land/manpower) compared to petroleum extraction. It tends to only happen for individual use, at small scale; or when heavily subsidized from taxes on petroleum products.
Just to make sure, did you see the edit of my comment above? I checked out the land cover in Finland, it is actually a fairly high percentage trees and I did some math on putting wind in the other places.
Now that I'm writing this I realized a major flaw: not looking at https://globalwindatlas.info earlier. It turns out that Finland looks about average (just eyeballing it, I can't figure out how to use this area energy yield tool, it just gives me a blank image instead of a simple number).
Now you are just making things up. The bigger and stronger trees are, the more valuable they are as timber. But there is plenty of non-forest land to use, and wind is wholly compatible with mixed use with developed farm and pasture, which is why we see that instead.
Timberland owners (at least in my experience owning a lot of timberland) need to time market conditions quite a bit to make a profit. If someone is lucky, an offer for the land CAN coincide with good market conditions for the specific timber they have at the state they have it, but that is far from guaranteed.
All the species I happen to have a good stock of went crazy high earlier last year, then crashed hard due to burn damage to forests in other parts of the state (from over 100% increase in margin, to negative margin) in less time than it would have taken for me to get the paperwork through the state to harvest them.
Depending on market conditions, it could be very expensive to clear, to wildly profitable to clear, but no one is going to sell it to them for less than the profit they’d make in a case like that.
Which is not a very gracious spelling of "Sorry, my comment you replied to was stupid; I retract it and apologize", which I'm sure was what you were trying to convey.
No, he is pointing out very real impediments to wind power build-out in forsests.
> If trees could be a problem,
As has been convincingly shown elsewhere in the subthread that they can, if one were stupid enough to build one's windmills among them.
> they would be built in ways that trees would not be a problem, full stop.
i.e. not in forests. Which was user @lazide's point all along.
And if you were going to say -- as the remains of your argument seem to be boiling down to -- "So don't build windmills in forests then", YTF did you say that to @lazide and not to @Aachen?
You have contributed exactly nothing of any substance to the discussion.
Did you?
Really a choice to go nuclear. Not a necessity.
In heating, heat pumps (geothermal and others) are growing fast (market share 16% in 2021).
Still, wind and other unstable sources can never be the dominant source in society. We need dependable power and for that you need nuclear unless something drastically changes with energy storage.
In 2009 hydro power was 15% of their electricity. An old number, but it's not too bad, it's something.
Basically, yes.
Especially as I'm in the UK, and we decided to build a copy of it (Hinckley Point) even after all the flaws become known.
Now we should figure out where to build third! It should go even better.
It should be noted that Hinckley C is penciled in to start operations in 2026. Hopefully if they give Sizewell the go ahead this year it will be in service 2031.
Chernobyl! Fukushima! Radiation! Waste! Death! Death!! DEATH TO ALL HUMANITY!!!
If Russia didn't have nukes, its imperialistic ambitious would be curtailed. The ability to shield conventional assaults behind a nuclear threat is destabilizing for the rules-based world order.
In my particular country, a major chunk of the public budget goes towards paying fines to EU for use of coal, all while our government periodically passes bills allowing it to borrow more money from the central bank, increasing inflation. Negotiations with neighbouring autocratic countries can be pretty tough, when they can threaten us and rest of Europe, which is going to put pressure, with stopping energy transmission. Energy shortages in some parts of the country were a regular occurrence for decades, even before the current political problems.
Lack of nuclear plants does nothing to prevent a nuclear war, while it harms us on many very tangible levels.
I agree that dependence on geopolitically and environmentally problematic fossil fuel sources is a pressing concern.
But yet [your country] is not lost?
(People get upset at the implication that one country would take over another country, but the people of North Korea would probably not be worse off if that happened. Instead they suffer greatly because nobody can help them.)
Their first nuclear test was in 2006. Even their production of refined uranium and plutonium only began in the 80s, decades after the war came to a standstill.
If anyone is upset that the people of the German "Democratic" Republic got to join the rest of "We, the people" in a free Federal Republic, they're cordially invited to go fuck themselves.
The same would go ten times over for anyone feeling that way about the much more oppressed North Koreans.
I'd sure like it if less inherently dangerous technologies were further along. But every year they are gaining.
And they're right about it not being the cheapest option, so what can you say? They win the argument.
Next time you meet the person is at a protest where they don't want a solar farm where there is now a nice forest or pasture, no 24/7 moving shadows from huge wind turbine blades and that's after they pushed for a law to require more space between the edge of town and the nearest turbine, protesting for fish rights when hydro is being proposed (if that's possible in their area in the first place)...
People also love to gloss over that electricity is 10% of the problem. Whenever you see a headline about Germany having run on 90% renewable power last month or whatever, mentally replace that with 9% because energy used in transportation, building heating, etc. don't count towards this. And then we haven't even touched upon the problem of cement/steel/plastic yet, we're going to need breakthrough materials or negative emissions with capturing plants that, you guessed it, also require electricity.
It's apparently very hard to understand that we need to work on all fronts, not pick a partial solution and wait until that's exhaustively implemented (all reasonably available space occupied) 15 years down the road, then wonder why emissions are at record highs (see 2021).
Getting consistent funding for new projects is hard when every other project in history has over run both costs and time widely.
But yeah if we argue for another five years before getting started on at least the legislation/planning stages (after which we could still declare it a sunk cost, based on how the situation looks in 2027), we might as well forget about it.
Firstly, the plant above has costed more than 3x projected time or money, so doubling is not going to solve anything.
Secondly, forget civic planning, could you or I go to our companies and say just double by budget because we don't know how to plan well ? What is the guarantee our plan is at least 50% accurate ? i.e. only 2x is enough ?
Poor planning cannot be solved by increasing budget (time or money), even in non public projects, work has tendency to get expanded to meet the budget, basically if Norway had thought 2x the $3B and actually budgeted $6B, they would likely have spent $20B in the end.
All this is only for operational life of the plant, it does not even include long term costs of waste storage because no one can even model that well enough or budget for it today.
I am not saying we shouldn't do nuclear, we really should, but truly commercial plans are meaningless unless we can handle costs better, We should invest more on that, there is encouraging work in SMRs(Small Modular Reactors) that could potentially address these concerns, until then most plants are experimental high risk projects from a public plan perspective.
Agriculture and industry are tough nuts to crack. With electricity, transport and heating, it's a problem of scaling out. With agriculture and industry - we don't even have a blueprint yet
Takes decades to build, will be too late for climate change.
Uranium is also a finite resource
By any objective metric, nuclear is by far the best choice for stable base power generation.
"But what if it explodes" - and there goes all rationality.
Humans will take constant death from coal power plants rather than a minuscule chance of a larger catastrophe in a nuclear plant.
The only way these are remotely economical is when they are funded by the tax payer before the are built, while they run, and after they close down.
Any examples that goes against that? I'd be very interested to learn about them. I think as a way to ensure energy independence and remove fossil fuels they are good, but we cannot pretend they don't come with massive costs, and don't yet pay their own way.
And we do not really have any storage available - the only systems that are 1) not experimental 2) usable for anything other than frequency stabilisation; are the pumped hydro - and those are geographically limited. At least when it's windy, you can use wind turbines as sinks for stability. Intermittent nature of solar and wind is too intermittent for most industrial sinks.
Meanwhile unpredictable nature of generation from wind and solar push the grid to buildout LNG/petroleum powered gas turbines, due to their very short delay on ramping up/down (IIRC, second only to hydro). So you end up in situation where market approach to electricity is going to prevent decarbonisation, unless you hugely upend what is being bought on the market.
Personally I've been thinking of electricity market paying only for predictable (aka "dispatchable") low-carbon power plants, or at least with huge priority. Solar and Wind could still compete on such market by being paired with storage systems into Virtual Power Plants (something that already exists), and the rest of the generation would be sold on spot market during peaks, or preferably to dedicated sinks like green hydrogen production.
Thus far, a renewable euro has been just overwhelmingly better used to build out generating capacity, even where intermittent. The only problems in storage are picking which will be cheapest or otherwise most valuable -- e.g. hydrogen, ammonia, and liquid air are entirely the latter -- and that by waiting, you get more for your euro. Storage cost is plummeting much faster even than solar, and solar is already so cheap that building 2x, 3x, 6x overcapacity is in easy reach.
The cheapest, most efficient present storage is pumped hydro, which can be used in very many places where native hydro generation cannot be, i.e. almost anyplace with hills. But iron-air battery factories are under construction, for very cheap and safe storage, and that will compete with many other alternatives. Each has strengths for certain places, all work, and operating cost is in all cases very small, so building "the wrong one" just means you spent more up front than you maybe had to.
Trotting out the "ooh, storage" argument only demonstrates you don't have one.
So if you want to base an electrical grid solely on nuclear power without additional fossil fuel plants, you need either a lot of often unused (and thus very, very expensive) nuclear capacity or some kind of .. storage. It's similar to renewables in that regard, although much more predictable and reliable (with exceptions, such as france this winter).
* Lots of public opposition due to the public being scared of nuclear waste, nuclear accidents, etc. The public far prefers taking on invisible risk (like the lung cancer risk from coal/oil/gas emissions) than the huge event risk of a nuclear meltdown, even if the overall harm to human lives is higher.
Difficulties in managing waste
20 years ago I was all for nuclear, then I looked at terrible projects in Europe, like in the Finland and the UK, and realised that it's too little too late. Europe can't build nuclear, so rather than trying to fight a losing battle for another 20 years, Europe should be massively investing in what it can do (offshore wind, tidal, solar, pumped hydro)
That is unless we sanction all nations that have nuclear weapons and blockade them from international trade until they get rid of them and subject themselves to being open to inspections for couple centuries.
That's the happy path.
The failure path with an unhinged dictator causing global destruction also gets much more likely.
- Cost. Literally billions of dollars, all upfront. This one was budgeted at $3B and ended up costing $10B+.
- Inflexibility. Almost all of the cost is in building one, so if you aren't running it basically 100% of the time at 100% capacity you are losing money.
When it comes to $/MWh, nuclear simply can't compete with fossil or renewable when demand is low. And you can't run it to pick up high demand because it gets even more expensive. The private market is simply not interested in them, unless they get a government guarantee that forces their production to be bought at a fixed price.
And there's of course the whole safety and waste argument, but I consider that to be secondary. All in all, nuclear is a could-have-been and mostly a side-effect of nuclear arms development. Neat technology, but there are way better options.
https://whatisnuclear.com/economics.html
https://whatisnuclear.com/fukushima.html
...etc.
1) If markets valued the low-CO2 nature of nuclear, they’d be doing better
2) Multiple hypothetical approaches to reduce nuclear costs are ongoing. No one knows for sure if any of them will work, or which one will work best
3) Factory-produced large reactors on floating platforms is a surprisingly intriguing idea to make reactors cheap
or: 1) make everything else more expensive so we look better
2) let me consult the magic orb because I have nothing in my hands
3) I have a nice idea
Meanwhile we have HERE just another example of hilariously expensive reactor. Actual facts. Waved away with theories like "we don't have the people with experience anymore" which leaves you with the thought: should inexperienced people build nuclear reactors at all?
You mean an "Impressum"? That's just some weird thing that AFAIK (almost?) only German Web sites have, because they're required to by German law. The vast majority of sites on the World Wide Web get by just fine without it; it's not like that's some kind of minimum requirement for a reputable site.
So saying "a Web site without an imprint" as if that in itself somehow showed the site were somehow bad is, if it's about a non-German site, just stupid. HTH.
We have to build lots of bigger, standardised reactors which will then reduce the cost due to experience and economies of scale. But then of course someone has to subsidise the tens/hundreds of billions in upfront investment to get to that point.
Where as with renewables this was all done decades ago. And we are now at the point where it is orders of magnitude cheaper than nuclear. And getting cheaper by the day.
Is it because of political activism and some occult groups of interest which have their own agenda?
Be Carbon Free in 10 years and sell excess energy to neighbours.
Do it now.
Putin has taught us that politicians can actually do stuff when they are forced into an existential crisis, maybe they should do something here as well.
I don't claim to have the answers but I suggest there are many opportunities that are worth pursuing.
I imagine it's almost impossible to manufacture nuclear weapons 'quietly' with waste and sanctions/agreements stop this happening, while countries that go against these are able to manufacture nuclear weapons anyway (North Korea). So I don't think this is as big a risk as suggested.
The rest seem solvable by focusing on better secure designs and then moving from Uranium to another source. I don't know the difficulty of this but I can't imagine it's insurmountable?
Not sure why I even bothered digging into it, but for example one later point is also misleading: "uranium resources will be depleted by the end of this century".
I think I found the source (not that they link it, that would be too easy, but by ducking around for this number):
> the total identified amount of conventional uranium stock, which can be mined for less than USD 130 per kg, [was found] to be about 4.7 million tonnes. Based on the 2004 nuclear electricity generation rate of demand the amount is sufficient for 85 years, the study states. Fast reactor technology would lengthen this period to over 2500 years.
> However, world uranium resources in total are considered to be much higher. Based on geological evidence and knowledge of uranium in phosphates the study considers more than 35 million tonnes is available for exploitation.
https://www.iaea.org/newscenter/news/global-uranium-resource...
I'm not sure how the "city of vienna" can read this and summarize it down to say that we'll plainly run out of uranium by 2100. That's just not what the source says. Maybe that's what makes this "reference" "handy" for people with a certain preexisting opinion?
The same bullet point continues with some other interesting claims, let alone the rest of the page, but let me quickly close that tab before I feel inclined to go down more of these rabbit holes...
What exactly about this do you not buy?
And what is your solution for storing nuclear waste safely for hundreds of thousands of years?
See https://whatisnuclear.com/chernobyl-main.html#again
Or even just another comment in this very thread: https://news.ycombinator.com/item?id=30653778
Or the fact that it hasn't happened despite hundreds of active nuclear power plants around the world (not all in countries that you would expect to have high safety standards).
Or the safety statistics in general: https://ourworldindata.org/safest-sources-of-energy
Same with the waste issue. Nobody asks what the proposed solution is for CO2 storage (it will remain for billions of years! The horror!) when proposing to keep open coal/gas plants a bit longer until we have solar/wind/hydro+storage all set up, but with nuclear we need to find more reasons for the phase-out.
Here's another info page: https://whatisnuclear.com/waste.html
> If these materials are burnt in fuel through recycling, nuclear waste would only remain radioactive for a few hundred years
And that's ignoring that we're also managing to deal with the waste so far just fine, also without recycling.
(The tally is at 40 minutes time wasted for these two answer so far, also because most of the previous one was 'researched' and written on mobile. How long did it take to ask the question? This is why I contemplate templates.)
https://en.wikipedia.org/wiki/Onkalo_spent_nuclear_fuel_repo...
We got from horses to Lamborghini Huracan in a century.
> And what is your solution for storing nuclear waste safely for hundreds of thousands of years?
While it's a problem, it's actually a fairly tractable one, because the volume of high level waste is small and it doesn't leave the plant as part of normal operations. For coal power, for contrast, we store much of the waste in peoples' lungs.
"Lasers could cut lifespan of nuclear waste from a million years to 30 minutes"
https://news.ycombinator.com/item?id=30652334
Obviously this particular idea is still blue-sky but as technology improves, I'd like to think we'll be able to solve problems like this within a few decades.
(although I'm still waiting for my Mr Fusion, Flying Car etc).