The Ulink extension was part of the original proposal, so it should be counted against the original budget and timeline as well. The U-district station didn’t open until 2016, 20 years after being voted on and 10 years behind schedule. The extension also cost $1.8 billion on its own.
From the same wiki page I cited earlier:
> The ballot measure failed to pass on March 14, 1995, and the light rail line was shortened to 25 miles (40 km), between the University District and Sea-Tac Airport. Voters approved the $3.9 billion package on November 5, 1996
> The initial segment identified and approved by Sound Transit later that year shortened the line to 14 miles (23 km), between Downtown Seattle and a southern Tukwila station near Sea-Tac Airport. The remaining routes to the airport and University District were sent back to the planning stage, and re-organized into separate light rail projects.
> Planning of the Portage Bay tunnel between Capitol Hill and the University District was suspended due to higher than expected contractor bids, attributed to difficult soil conditions.
> The line was extended north to University of Washington station, via Capitol Hill station, on March 19, 2016, via a $1.8 billion, 3.15-mile (5.07 km) tunnel.