That's testing one source; and you CAN do that but you may find that there are things you didn't realize because the grid was actually UP.
For example, the entire station may be disconnected from the grid, but somewhere in the system is a Siemens device that for whatever ungodly reason needs to access the internet, which works when the grid as a whole is operational but fails when it can't get cell service.
And even if those stations work correctly, you still haven't verified that the actual plan is operational because you haven't actually done the black start; perhaps the grid divisions are incorrect and the first load you try to apply will brown out the start source.