>And it's way faster since you don't spend months preparing a site and building forms.
What size house are you building that it takes months preparing a site to build foundations? Sub 2000sqft houses are built to completion in 90-120 days if weather doesn't delay things. It only takes a couple of weeks from clearing the site, digging the trenches, lining the moisture barrier, laying the rebar and forms, then pouring the cement. The formulas today cure very quickly. From the day of the pour to the start of framing is practically the blink of an eye