The study might show that the upgrades required to inject power at a project location and maintain system stability and reliability are too costly and the project can’t proceed as proposed.
The studies are usually performed in the order that the requests are received.
Project proponents are often unaware of where on the grid the most cost effective interconnections are for a given project size.
The feedback loop between proponents and utility could be tightened up if the utility would publish a map showing available capacity or cost to upgrade vs new capacity for different locations on the grid.
That is one way the utility could meet the demand to perform the studies faster with the same number of quants.