HVDC is needed when you build between two non-synchronous areas like France and UK. Also if you don't have the option to build pylons and need to go underground/underseas, AC lines will suffer from capacitive load. the longer the line gets, the more capacitive load will be present, and so you can't build very long underground/underseas AC lines.
Since HVDC has significant fixed costs, it's not relevant for shorter lines.