What projects in developed countries have used cut and cover recently? In trying to find out, I see that HS2 under west London and the Canada line under Vancouver chose tunnels over cut and cover because it was cheaper.
What projects in developed countries have used cut and cover recently? In trying to find out, I see that HS2 under west London and the Canada line under Vancouver chose tunnels over cut and cover because it was cheaper.
Canada Line was mostly Cut-and-Cover - only the bits below downtown and crossing below the water were bored, the bulk of the underground was done cut and cover for cost and speed to make sure it opened for the 2010 olympics.
It was not a popular choice - not really announced before the project was approved, and local businesses along the route took a big hit.
Vancouver's current Broadway Line Extension is being done with TBMs to avoid the impact that the cut and cover canada line segment construction had.
Not really a new project, but parts of the subway in Stockholm are cut and cover. One of those tunnels (from the 1930s) has been leaking in water for some years and is up for a total overhaul, so basically digging up everyting and doing a new cover.
The section is 8 m wide and 925 m long, projected timeline is 6-7 years starting this fall. It will be a massive project, as one of the busiest streets in Stockholm is directly on top of it.
I know in Sweden the Västlänken project partially used cut-and-cover at least for the part going southwards..
Case in point – the Karlsruhe tram tunnel (listed in that dataset as simply "Tunnel Boring Machine") used a tunnel boring machine for the main east-west tunnel, but a combination of NATM and cut-and-cover for the north-south branch. The stations and the associated road tunnel project were all cut-and-cover, too.