Moving more air through the tunnels, adding A/C systems - both have a problem of needing room up on the surface for blowers and compressors, something that is hard to do in modern London. Tough problem.
Moving more air through the tunnels, adding A/C systems - both have a problem of needing room up on the surface for blowers and compressors, something that is hard to do in modern London. Tough problem.
How many watts are dumped into onboard heat-generating resistors on the trains in the most heat-affected lines per week?
Should regenerative braking be disabled in aboveground trains when heat impacts reach uncomfortable levels in belowground tunnels?
> Regenerated braking energy is transmitted to the London Underground high voltage distribution network
If regenerative braking oversupply is inducing higher temperatures belowground through on-train resistors, then only an operational change to aboveground mode would be required to minimize that induced heating during times of thermal need.
(Obviously longer-term solutions with non-zero capital expenditure exist that could be pursued in parallel.)
I will guess that the limit is how much regen current can be passed back from the train into the supply system through the power supply rails / pickup shoes.
If I were making (confess, yes, untrained outsider) suggestions, I'd add water tanks to the trains, use the resistive braking to heat the water (not ambient air) during the trip, then change out the now-hot water for cold at the destination layover points. Not thinking this is a particularly creative solution, sounds like the "pull trains full of ice" already noted. Also this is off-the-cuff, so welcoming critiques!
Speculate: district level heating (wikipedia entry: https://en.wikipedia.org/wiki/District_heating) using heat pumps to draw out the tunnel heat; not sure if that is too complex altogether, maybe it would work as a longterm maintenance process but not as a 'fix the current problem' one...?
It’s not that simple. You can’t just treat the entire line as some kind of perfect conductor that allows to you move unlimited amounts of energy around. In reality there’s issues with both the conductive capabilities of the lines themselves, but there’s also the simple problem that train lines aren’t generally electrically connected end-to-end for a few reasons.
1. You don’t want trains pulling power down more of the line than necessary, when it’s more efficient to draw power from other parts of the high voltage grid.
2. You don’t want a single track fault to cause your entire line to be forced to disconnect completely.
3. You don’t want your line to accidentally become a power carrier for electrical grid, just because the two ends of your line a physically located far enough apart that they experience different grid conditions.
As a result most train lines are broken up into electrically isolated segments, each with its own distinct power supply. So you could turn of regen on overground trains, but unless they happen to be sharing a section of track with underground trains, it doesn’t create any additional capacity to dump breaking energy into.
https://railknowledgebank.com/Presto/content/GetDoc.axd?ctID...
Also:
> A super capacitor is being used in a substation by Docklands Light Rail in London, UK
So at least they were considering what to do about this fifteen years ago. I wonder if they've made progress?
Additionally you’re making the assumption that line voltages are stable and constant, and can be tweaked as needed. They’re not, they’re some of the most noisy, electrically unpleasant power systems in the world, with voltage bouncing up and down as trains accelerate and decelerate, consuming up to a MW each under peak load.
Power distribution companies hate providing power to train systems because you need so much infrastructure to handle the noise and prevent the train line from seriously degrading the local power grid. The substation that connect train lines to the power grid are constantly having their switchgear trip in and out as the huge spikes in demand cause the equipment to momentary disconnect to protect downstream equipment.
So creating headroom for extra regenerative breaking isn’t a simple thing to do. When each train can instantly consume as much power as 10 households all maxing out their power supply, electrical systems stop behaving anything like “normal”.
see https://tfl.gov.uk/corporate/transparency/freedom-of-informa...
Seems not trivial to just put extra batteries and the circuitry for regen breaking charging in.
It may be better to install such batteries somewhere on each track circuit as fixed stations, that can vent their charging and dispersal heat away from passenger tubes, rather than mobile — assuming that onboard emergency power needs are already met.
That's not really the problem; the problem is there is _no space_. Ever been on a London Underground train? You certainly wouldn't want the interior getting _smaller_.
I'm sure they'd consider the worst-case scenario, and at present that's probably some serious arcing within a motor causing a fire. Cutting the track power (easily done by the driver) then makes that a fire that can be handled with water and/or foam.
Smoke from large batteries would be very hazardous.
That said, a typical shitty single-hose monoblock air conditioner has 9000-12000 BTU/h of rated cooling capacity. 12000 BTU/h is also known as "one ton". Sometimes, stupid units can be helpful, because "one ton" of cooling is what you get if you dump one ton of ice (short ton, of course) per day in the place. So you'd need a lot of ice, many tons per station, to make a significant difference.
Either way, since this is such an obvious idea, and they had a competition to solicit solutions, I'm sure this was evaluated and discarded - although it would be interesting to read the official analysis of the idea and learn why it wouldn't work.
Just about every abandoned station, elevator shaft, and maintenance tunnel on the network is already fitted out with huge fans where possible.
TfL also runs a semi-continuous works project that looks a custom and novel one-off cooling solutions that can be retrofitted into whatever space is left. Including complicated hydronic systems that pump around huge quantities of water where the infrastructure allows for it.