Points are not intrinstic or objective attributes, like the sky being blue. The scale is arbitrarily chosen by any given team, and relative to past work. But a common reference point is that 1 point is the "smallest" feature worth tracking (sometimes 1/2), and 20 points is usually the largest individual feature a team can deliver in a sprint. So it's common for teams to be delivering something between e.g. 50 and 200 points per sprint. Teams very quickly develop a "feel" for points.
> And then another matter is that points do not correlate to who later takes that work.
Yes, this is by design. Points represent complexity, not time. An experienced senior dev might tend to deliver 30 points per sprint, while a junior dev might usually deliver 10. If a team swaps out some junior devs for senior devs, you will expect the team to deliver more points per sprint.