Eglington Crossing light rail - 6 year delay (to 15 year total) with a tripling in cost to $15B - so about $1b per kilometre of light rail.
Peace River hydroelectric - costing double ($16B) original budget.
Vancouver wastewater - a 4x budget creep (to $4B) and a 10y delay so far - it hasn't opened yet.
My point is that it's not only nuclear fission power plants that are grossly underestimated in terms of cost and complexity, but rather, all large infrastructure projects.
Just happens that on top of all that, the estimated numbers for LCoE, payback, clean-up, opex, etc for nuclear fission are also misrepresented (or misunderstood, depending how cynical you are).