You can’t get a grid tie for those panels in most of the US right now. The process for connecting to the grid is done serially, and requires a large study for any new generation.
You'd be wrong. Projects get evaluated FIFO, and each has to do a grid impact study. Data centers are buying other generation projects to get a better position in line. This is all the result of bad regulation.
My state allowed the power utilities to charge a modest fee ($10,000 to $100,000, depending on project size) before a yet-to-be-built data centre could demand a large amount of electricity. The amount of planned data centres went down by an order of magnitude. The truth is that most of the data centre builders (not all) do not want to be responsible citizens and are simply extracting value and wealth from other people, including from the power utilities and grid operators.