Grid connection permits don't take as much time as, for instance, real natural gas turbines, which currently have a three to five year lead time. The jet turbines are the "right now" solution while they wait for those. While it's possible some jet-powered datacenters have some grid tie permits in process, I have so far found none. Permit applications are public record almost anywhere, so it's not tough to check