In our office we work around 8 hours per day. We use Agile (Scrum) but we count only 6 hours per day. We recognize that we spend around 2 hours in overhead tasks (informal meetings, tasks not listed in the sprint and some not-job related work.
The only problem that we found is with people coming from consultancy. They are not confident with only having 6 hours per day as they are used to log 8 hours and bill them to a customer.
In general, the team is pretty comfortable with the approach of using 6h/day for estimations in our tasks.