Unless your numbers are completely random just for the example, deciding to run an 1,000 hour project with 10 people is a disaster by itself. How would you involve 10 people in a short 3-4 weeks project?
The numbers were only to make the point that hours are more easily accepted when it's split among a larger team. Yet the same quality is expected when a single Full Stack dev does the project in 1/4 the time and budget?
One validator, six testers, three developers. Not at all uncommon in certain industries.