$120m/year for apparently unnecessary IT capacity would be hard to hide even in government contracts...
$120m/year for apparently unnecessary IT capacity would be hard to hide even in government contracts...
Not impossible at all to believe they could cut $10M/month from could spend at a big enough company just by trying.
For an engineering team of ~1000, just the build servers will cost about $1-5m a month (depending on what's being done there).
$1M/mo will rent you about 300 c5d.24xlarge servers, at on-demand rates (and of course no medium or large enterprise is paying the higher on-demand rates). I'm pretty sure we're running somewhere on the order of 10 build servers, and they're maybe 4xlarge or 8xlarge boxes.
Let's say we pair engineers up just to make my math a little easier here. One engineer's allotment goes to compute resources, another goes to storage.
At the low end, that's a 32 core/128GB RAM build server with 10TB of storage per pair.
At the high end, depending which way you spec that out, that's 96 core/385GB RAM with 50TB per pair.
What the hell are you guys building?!