I agree there are other things that can go wrong, but the "two contracted gas turbine black start sources didn't work" problem does still seem like something that probably could have been avoided with regular testing?
It's the same reason that datacenters don't just run the generators every month, but actually switch over to generator power and disconnect from the grid to verify it works (and if it doesn't, hopefully the batteries last long enough to get back to the grid!).