Can you elaborate on why we wouldn't share the carefully estimated project plan breakdown with Level 1? I'm not disagreeing, just curious - one would think that with doing all the work to achieve a solid project plan breakdown and Gantt charts and such, it would behoove you to express this to management who is salivating over tangible examples of progress... I understand we don't want to show technical to non-technical, but part of the good project plan is the fact that we can show a roll-up of the tasks, so the abstraction is visible. It's hierarchical.