> "Iran is 6 weeks away from building nuclear weapons"
It is the breakout time, not the schedule.
It is incredible to me how pervasive the misunderstanding of this statement is!
I've had real-life conversations with project managers just like this:
PM: "How long would this project take?"
Me: "One month."
... two weeks later ...
PM: "How long would the project take to finish?"
Me: "One month."
PM: "You said that two weeks ago! It should only take two weeks to finish!"
Me: "Why would you think that? We never started the project! It wasn't approved. You didn't approve it, personally. The effort is four weeks. If you approve and we start today, it will still take that long to complete."
... two more weeks later ...
PM: "Why isn't the project finished!? You said one month a month ago!"
Me: "... wat?"