> I give an estimate with an error margin, that is usually larger. eg something like "that will take about 3 weeks, plus or minus 2 months"
I can’t tell if you’re being serious. How do people respond to such a non-estimate?
I can’t tell if you’re being serious. How do people respond to such a non-estimate?
My approach also helps start a discussion about how to reduce the size of the plus/minus bit, such as reducing scope, breaking into multiple pieces etc.
And the minus bit coming to negative time works well too. It becomes a decision about using what is already there even if not perfectly suited versus doing the new work, and how much of it to do.